Page 11 - MEOG Week 04 2022
P. 11

MEOG                                            TENDERS                                               MEOG


       KOC to launch pipeline tender





        KUWAIT           STATE-OWNED Kuwait Oil Co. (KOC) will   “KOC decided to cancel those projects as
                         soon launch a pipeline construction contract to  part of spending rationalisation plans and opt
                         support its Jurassic gas production facilities fol-  instead for expansion of the existing facilities,”
                         lowing the award of two major deals in Q4 2021.  one source was quoted as saying, noting that the
                           According to reports in local media, the  projects were central to KOC’s target of achiev-
                         $100mn contract is expected to be made availa-  ing 950 mmcf (26.9 mcm) per day of free gas
                         ble to bidders through the government’s Central  capacity by 2023. JPF-4 will be located near the
                         Agency for Public Tenders (CAPT) later this year  Sabriya field in North Kuwait, with JPF-5 situ-
                         and will be linked to JPF-4 and JPF-5.  ated around 10 km to the east.
                           The main contracts for the two processing   In October, the Ministry of Oil (MoO) and
                         facilities were awarded in November, to Chinese  KOC’s parent firm Kuwait Petroleum Corp.
                         company Jereh Oil & Gas Engineering Corp.  (KPC) said the emirate would raise its maximum
                         and local firm Spetco International Petroleum  sustainable capacity for oil production from the
                         Co. respectively. According to sources close  current 2.6mn bpd to 3.5mn bpd by 2025 and
                         to the awards quoted in the local Arabic-lan-  4mn bpd a decade later, with the latter target
                         guage Al-Anba, Jereh’s winning bid was valued  brought forward by five years.
                         at $426mn, while Spetco’s was $398.2mn, both   KPC CEO Hashem Hashem said KOC would
                         around 14-20% below the level anticipated when  achieve the increase through work on gathering
                         bids were sought in Q3.              centres, the expansion of water-handling and
                           While bidders were prequalified during Q2  water injection facilities as well as upgrades to
                         after the submission of the required $28mn  existing Jurassic production facilities and the
                         deposit, the increased competitiveness of the  addition of new production units and wells.
                         bids is thought to have stemmed from Kuwait’s   Kuwait News Agency (KUNA) quoted
                         greater budget strain amid ongoing issues related  Hashem as saying that KOC’s projects included:
                         to the coronavirus (COVID-19) pandemic and  “Upgrading current Jurassic production facili-
                         political instability.               ties and establishing two additional facilities to
                           The contracts for JPFs 4 & 5 cover the con-  increase light crude production. This plan will be
                         struction of processing facilities and pipe laying.  implemented in combination with an integrated
                           The wider project is expected to have a total  drilling programme of 500 wells per year on
                         capacity of 100,000 barrels per day (bpd) of  average and around 2,000 wells workover.”
                         light crude and 300mn cubic feet (8.5mn cubic   The news followed reports in September that
                         metres) per day of gas. However, in July, KOC  the company would drill an extra 300 wells per
                         was reported to have cancelled plans for JPFs 6 &  year, taking the annual total to 700, as part of a
                         7, which had been anticipated to cost a combined  $6.1bn capital expenditure on exploration activ-
                         total of $1bn-2bn to complete.       ities over the next five years.™








































       Week 04   26•January•2022                www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14   15   16