Page 5 - MEOG Week 27
P. 5

MEOG                                         Commentary                                               MEOG








































                         bpd by the end of this year and to 4.75mn bpd by  then see ratqa’s production lifted to 325,000 bpd,
                         the end of 2040, up from the current 3.1-3.2mn  while the final phase envisages output from the
                         bpd. in late 2019, the 2020 target was reported to  two fields totalling 430,000 bpd. Apparently una-
                         have been pushed back to 2040.       shamed of the four-decade delay, a company offi-
                           However, positive news has come in the form  cial was quoted noting that attempts had been
                         of output from the long-delayed Lower Fars  ongoing to develop heavy oil at ratqa since 1979.
                         heavy oil project finally hitting the market in   Meanwhile, Baker Hughes and Halliburton
                         recent months. Production from the develop-  have also awarded rig contracts over the past 12
                         ment’s two fields – South ratqa and Umm Niqa  months for efforts to increase production from
                         – has now reached a first phase plateau of 75,000  on- and offshore areas respectively.
                         bpd since it began in February.        While the progress onshore appears to be
                           The broader ratqa asset was discovered in the  broadly cheering for Kuwait, it remains to be
                         late 1970s, but efforts to develop the field have  seen whether under current market conditions,
                         been largely stifled.                plans for long-awaited offshore production will
                           Lengthy and ultimately fruitless efforts by  gain much traction.
                         successive governments to persuade MPs to   However, Al-Khafji offers Kuwait and Saudi a
                         allow KOC to enlist substantial iOC assistance  relatively swift, and certainly cost-effective, addi-
                         were largely to blame for the delays, com-  tion of 65,000 bpd each, with more to come. For
                         pounded by the notorious slowness of state  Saudi, this increment will change little, but for its
                         decision-making across the board. The state  northern neighbour, the increase is much more
                         upstream firm lacks experience of such challeng-  meaningful.™
                         ing production.
                           However, in early 2015 the UK’s Petrofac was
                         finally awarded a $4.2bn engineering, procure-
                         ment & construction (EPC) contract to execute
                         the first phase of the so-called Lower Fars Heavy
                         Oil Project, calling for production of 60,000 bpd
                         by this year.
                           A multi-phase project aimed at pump-
                         ing more than 200,000 bpd by 2030 has long
                         been envisaged. However, the latest statement
                         stretched out the timetable to 2040 and also
                         covered the development of heavy oil at nearby
                         Umm Niqa.
                           By 2026/27, KOC aims to increase ratqa’s
                         output to 120,000 bpd, rising to 230,000 bpd by
                         2030/31, with production at Umm Niqa seen
                         climbing first to 50,000 bpd and then to 80,000
                         bpd over the same period. A fourth phase would



       Week 27   08•July•2020                   www. NEWSBASE .com                                              P5
   1   2   3   4   5   6   7   8   9   10