AfrElec                                    COAL GENERATION                                            AfrElec


       ABB allocates $325mn





       to cover cost of probe





       into Kusile plant






        ZIMBABWE         SWISS engineering group ABB has reached an  authorities regarding the remaining matters
                         agreement to sell back to Hitachi its remaining  related to the legacy Kusile project in South
                         19.9% stake, worth $1.679bn, in the Hitachi  Africa awarded in 2015,” said the statement.
                         Energy joint venture. Hitachi exercised its option   “Based on these discussions, ABB does not
                         to buy the stake in the venture formed from  believe that it will need to take any material
                         ABB’s Power Grids business in 2020, Reuters  additional provisions relating to these matters.
                         reports.                             The company continues to cooperate fully with
                           Separately, in a statement on September  the respective authorities and hopes to reach a
                         30, ABB said it was setting aside a provision of  final settlement with them in the near term,” it
                         around $325mn to cover costs related to inves-  concluded.
                         tigations surrounding the Kusile power plant in   As for the Hitachi deal, ABB said it does not
                         South Africa.                        expect to record any significant gain or loss as a
                           According to Reuters, ABB agreed in 2020 to  result of the sale. “ABB expects net positive cash
                         pay ZAR 1.56bn (then worth $104mn) to South  inflows of approximately $1.425bn upon closing
                         African state power utility Eskom to settle an  of the sale,” the company said in a statement,
                         investigation into improper payments and com-  adding that the transaction is expected to close
                         pliance issues related to the project.  before the end of 2022.™
                           “ABB is progressing discussions with relevant
















































       P10                                      www. NEWSBASE .com                      Week 39  29•September•2022