Page 9 - AfrElec Week 39 2022
P. 9

AfrElec                                   COAL GENERATION                                            AfrElec


       Zimbabwe’s $1.5bn coal-





       fired power plant project





       nears completion






        ZIMBABWE         WORK to expand a 920MW coal-fired power  generation dynamics and ensure that the nation
                         plant in western Zimbabwe is nearing comple-  will have sufficient electricity by adding new
                         tion, according to reports. The $1.5bn project,  units,” Construct Africa writes.
                         whose construction started in March 2019,   “The additional capacity will help tide over
                         entails adding 600MW to the existing capacity.  the nation’s energy deficit and improve the
                           United Arab Emirates-based Construct  socio-economic well-being of the country by
                         Africa reported on September 26 that construc-  attaining a balance between demand and supply
                         tion work is also ongoing on a 42-kilometre  for the daily usage of electricity at domestic and
                         962mm water pipeline from the Zambezi River,  international levels.”
                         to the Hwange Power Station.           Zimbabewan state-owned daily the Chron-
                           The new pipeline will increase the water sup-  icle reported on Thursday (September 29) that
                         ply to the power station from 3,500 to 6,000 m3  engineers at the Chinese-funded project are now
                         per hour and run parallel to the existing 900mm  synchronising the sub-systems of one of its units
                         water pipeline supplying the plant.   ahead of potential connection to the national
                           The new pipeline from the Deka pump sta-  grid in November.
                         tion is estimated to cost $48.1mn, and is being   “By and large, we are almost there. We are
                         funded by the India Exim Bank. Indian contrac-  above 93% complete for both units.  Unit 7 alone
                         tor, Afcons Infrastructure is constructing the  is at 97% despite the delays of more than a year
                         pipeline, which is expected to be completed in  because of COVID-19 and delay in payment,”
                         time for the commissioning of one of the two  project engineer Forbes Chanakira told the
                         new 300MW units at Hwange Power Station.  Chronicle.
                           “The Hwange Power Station upgrade pro-  Unit 8 of the project is set to be complete by
                         ject will help transform Zimbabwe’s electricity  the end of March 2023, officials have said.™









































       Week 39  29•September•2022               www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14