Page 8 - GLNG Week 26 2021
P. 8

GLNG                                              AFRICA                                               GLNG


       DFFE rejects Karpowership’s applications




       for LNG-to-power projects




        PROJECTS &       SOUTH Africa’s Department of Forestry, Fish-  in each port. (The powerships were to have a
        COMPANIES        eries and the Environment (DFFE) has decided  combined generating capacity of 1,220 MW.)
                         against giving Karpowership (Turkey) per-  DMRE selected Karpowership within the
                         mission to go ahead with three LNG-to-power  framework of an emergency effort to alleviate
                         projects.                            South Africa’s ongoing electricity shortages. This
                           DFFE announced its decision in a statement  effort, known as the risk mitigation independent
                         dated June 24. “The competent authority in the  power producers programme, was designed to
                         department has decided, after due consideration  make another 2,000 MW of generating capacity
                         of all relevant information presented as part of  available within a short period. However, DFFE’s
                         the environmental impact assessment process  ruling may prevent the Turkish company from
                         for all three applications in question, to refuse  meeting its obligation as a preferred bidder to
                         the applications for the environmental author-  wrap up agreements by the end of July.
                         isations,” it said. It explained the ruling by saying   A spokesperson for Karpowership told Reu-
                         that Karpowership had not yet had the time to  ters last week that her company intended to
                         assess the environmental impact of the projects.  appeal against DFFE’s decision. She also asserted
                           The Turkish company began seeking envi-  that Karpowership had been the target of a “mis-
                         ronmental approvals for the establishment of  information campaign” that had raised undue
                         LNG-to-power facilities in the ports of Coega,  concerns about the risks of the LNG-to-power
                         Richards Bay and Saldanha last October, when  projects.
                         it was chosen by the Department of Mineral   “Karpowership SA conducted a robust
                         Resources and Energy (DMRE) to execute pro-  public participation process, met all South
                         jects at these three sites. In its applications, it out-  Africa’s stringent environmental require-
                         lined plans for anchoring paired floating storage  ments and is confident that it will win the
                         and regasification units (FSRUs) and powerships  appeal,” she declared.™



                                                      AMERICAS

       Delfin requests delay to FLNG plan





        PROJECTS &       US-BASED  Delfin LNG has asked federal  which Delfin says bolsters its chances of entering
        COMPANIES        energy regulators for more time, until September  into long-term LNG offtake contracts.
                         2022, to bring the onshore facilities related to its   The company added in its FERC filing that it
                         proposed floating LNG (FLNG) export project  was “confident that it will secure commercialisa-
                         off the coast of Louisiana into service. This would  tion in the coming year”.
                         be the third extension for the project, which had   Delfin’s FLNG project would use existing off-
                         initially been authorised to enter service by Sep-  shore pipelines to supply gas to up to four vessels
                         tember 2019.                         that could produce up to 13mn tonnes per year
                           Delfin asked for its first extension in June  (tpy) of LNG. The plan is one of several proposed
                         2019, and had requested to have until March  for the US Gulf Coast, but is the only offshore
                         2023 to complete the project. However, the US  project among the proposals.
                         Federal Energy Regulatory Commission (FERC)   The company’s request for a further exten-
                         only gave Delfin a one-year extension, until Sep-  sion comes as momentum appears to be pick-
                         tember 2020.                         ing up for some of the other LNG projects in the
                           Delfin then succeeded in receiving another  region that have yet to reach the final investment
                         one-year extension in June 2020, giving it until  decision (FID) stage. For example, Tellurian
                         September 2021 to finish the project. However,  announced this week that it had signed a long-
                         delays have continued to plague Delfin’s plans.  term lease with the Lake Charles Harbor and
                         This time, when asking for this third extension,  Terminal District in Louisiana for the site of its
                         the company talked up what it believes to be  proposed Driftwood LNG terminal. Signing the
                         improved prospects for its project. It cited the  lease had recently been identified by Tellurian’s
                         global recovery from the coronavirus (COVID-  executive chairman, Charif Souki, as one of the
                         19) pandemic and said that spot and short-term  key remaining steps the company had to take
                         markets for LNG had “significantly improved”,  prior to reaching an FID on Driftwood.™



       P8                                       www. NEWSBASE .com                           Week 26   02•July•2021
   3   4   5   6   7   8   9   10   11   12   13