Page 15 - FSUOGM Week 25 2022
P. 15

FSUOGM                                PROJECTS & COMPANIES                                         FSUOGM


       Novatek head downplays concerns of




       Arctic LNG-2 launch delays




        RUSSIA           NOVATEK CEO Leonid Mikhelson sought to  financing for Arctic LNG-2.
                         downplay concerns about delays at the compa-  Arctic LNG-2 is under construction on the
       Novatek's head and   ny’s Arctic LNG-2 project at the St Petersburg  Gydan Peninsula, consisting of three liquefac-
       major shareholder   International Economic Forum last week, noting  tion trains each with a 6.6mn tonne-per-year
       previously warned that   that while there were “many problems, we strive  capacity. Novatek owns a 60% stake in the pro-
       the project might have   to meet the 2023 deadline.”   ject, while TotalEnergies, and Chinese compa-
       its schedule revised   Mikhelson had warned at a shareholders’  nies CNPC and CNOOC, each own 10% shares,
       because of sanctions.  meeting in April that the project, which at full  and the remaining 10% is held by a partnership
                         capacity will produce 19.8mn tonnes per year of  between Japan’s Mitsui and JOGMEC.
                         LNG, might have its schedule revised because   TotalEnergies announced in March that
                         of Western sanctions. As part of the fallout from  it would stop investing in Arctic LNG-2 and
                         Moscow’s war in Ukraine, a number of Western  would no longer include the project’s hydrocar-
                         financiers, contractors and equipment suppli-  bon reserves on its balance sheet. But the French
                         ers have withdrawn from Russia’s oil and gas  major also ruled out plans to sell its stake or any
                         industry, or intend to do so, which has raised  of its other assets in Russia, which include a
                         doubts about whether some of the country’s  19.4% stake in Novatek itself, a 20% interest in
                         more complicated projects can be implemented  the completed Yamal LNG plant, and 20% in the
                         on time.                             Kharyaga production-sharing agreement.
                           Speaking at SPIEF, Mikhelson warned that   Authorities in the UK and Canada imposed
                         the launch date for the two of Arctic LNG-2’s two  personal sanctions on Leonid Mikhelson in
                         phases may have to be revised, as Novatek had  early April. Nevertheless, on April 21, Novatek’s
                         planned to use foreign-made turbines which are  shareholders voted in favour of reelecting the
                         no longer an option under sanctions. The second  businessman, a major shareholder in the com-
                         phase is currently scheduled for launch in 2024.  pany, as their chairman of the board until May
                         Mikhelson also said there were no issues with  25, 2027. ™




       Karachaganak partners to send more gas



       to Russia's Orenburg plant





        KAZAKHSTAN       GAZPROM has agreed to ramp up the processing  Karachaganak have relied on Russian gas pro-
                         of gas from the Karachaganak field in Kazakhstan  cessing since its development in the late 1990s,
       The Orenburg plant has   at its plant in Orenburg, the company announced  because Kazakhstan lacks sufficient capability of
       been handling gas from   on June 17 at the St Petersburg International Eco-  its own. ™
       Karachaganak since the   nomic Forum (SPIEF).
       field's start-up in the   Gazprom has revised its contract with Kazakh
       late 1990s.       gas transport company QazaqGaz accordingly, it
                         said. Previously the partners had an agreement to
                         process 8.1bn cubic metres of gas from Karacha-
                         ganak in 2022, but the new deal covers an addi-
                         tional 570mn cubic metres of supply. The increase
                         in deliveries is scheduled from July 1, according
                         to Argus. In 2023, the volume of Kazakh gas will
                         increase again, to 9.33 bcm. And the two sides also
                         signed a memorandum on June 17 to eventually
                         raise this to 11 bcm annually.
                           The Karachaganak field lies in the Ural
                         region of Kazakhstan bordering Russia, and is
                         some 130 km away from the Orenburg plant.
                         Shell, Eni, Chevron and the other investors in




       Week 25   22•June•2022                   www. NEWSBASE .com                                             P15
   10   11   12   13   14   15   16   17   18   19