Page 13 - GLNGl Week 24
P. 13

GLNG                                            AFRICA                                                GLNG


       Audit shows Sasol may owe




       back taxes in Mozambique




        POLICY           SOUTH Africa’s Sasol may owe back taxes in  payments due, STV explained.
                         Mozambique, where it has allegedly overstated   As of press time, neither Sasol nor the
                         its recoverable costs. According to a report from  Mozambican government had commented on
                         the independent television channel STV, Sasol  the television channel’s report.
                         declared that its recoverable costs for opera-  Mozambique’s Ministry of Economy and
                         tions in Inhambane Province had reached of  Finance named Sasol as the best corporate
       The GCE audit     $148.7mn and $114.4mn in fiscal years 2017 and  income tax payer in the country in 2016 and 2017.
       results may also have   2018 respectively. But the preliminary results of   According to STV, the GCE audit results may
       consequences for other   the 2019 General State Account (CGE), an audit  also have consequences for other investors seek-
       investors seeking to   ordered by the Mozambican Ministry of Econ-  ing to extract natural gas from Mozambique’s
       extract natural gas from   omy and Finance, indicate that those numbers  Rovuma Basin, though on a smaller scale. Ita-
       Mozambique’s Rovuma   were inflated, the channel said.  ly’s Eni, which is developing the offshore Area
       Basin, though on a   The 2019 CGE audit shows that $50.5mn  4 block within the framework of the Coral
       smaller scale.    of the costs reported by Sasol in FY 2017 were  South LNG project, put its recoverable costs at
                         not actually eligible for recovery, STV reported.  $1.095bn between 2015 and 2017, and some
                         Another $49.3mn of the costs reported for FY  $22.2mn of the total has been deemed ineligi-
                         2018 were similarly ineligible, it said.  ble, the channel said. Total, which is developing
                           Assuming that these numbers are correct,  Area 1 within the framework of the Mozam-
                         Sasol appears to have overstated its recovera-  bique LNG project, claimed recoverable costs of
                         ble costs by around $99.8mn during the years  $904.7mn for the 2015-2017 period and has had
                         covered by the audit. If so, the cost inflation  $11.2mn declared ineligible, it added.
                         will affect the company’s tax obligations, since   Eni and Total have also not commented on
                         Mozambique deducts recoverable costs from tax  the audit’s findings.™

                                                      AMERICAS

       Venture Global takes steps




       forward on second plant




        PROJECTS &       US-BASED Venture Global LNG has been  noted that if Plaquemines goes ahead, it could be
        COMPANIES        authorised by regulators to proceed with limited  the only US LNG project to enter construction in
                         site preparation for its Plaquemines LNG project  2020 after most other developers delayed their
                         in Louisiana. According to the company’s web-  own plans.
                         site, early construction work at Plaquemines   Plaquemines LNG would have a capacity of
                         is scheduled to kick off in mid-2020, ahead of  20mn tpy, and has been estimated by analysts
                         financial close on the project late this year. The  to cost around $8.5bn. Venture Global says the
                         project would enter service in 2023.  facility would have an identical configuration to
                           Venture Global already has another export  Calcasieu Pass LNG. The company has signed
       Construction is already   terminal under construction in Louisiana – the  20-year sales and purchase agreements (SPAs)
       underway on Venture   10mn tonne per year (tpy) Calcasieu Pass LNG,  with France’s EDF and Poland’s PGNiG for vol-
       Global’s Calcasieu Pass   which is due to enter service in late 2022. The  umes from Plaquemines.
       LNG terminal.     company has reported that it recently raised   Venture Global also had a third planned
                         the roof on the second LNG storage tank at the  Louisiana export terminal in the works. The
                         Calcasieu Pass site. In addition, Venture Global  Delta LNG project would also have a capacity of
                         said in May that the first modules for the export  20mn tpy, though it may be constructed in two
                         facility’s 720-MW combined cycle gas turbine  10mn tpy phases. According to Venture Glob-
                         (CCGT) power plant had arrived at the site.  al’s website, construction is pegged to begin in
                         The Calcasieu Pass project is estimated to cost  the second half of 2021, assuming all regulatory
                         around $4.5bn.                       approvals are obtained on schedule.
                           The company’s push to advance construction   It would be surprising, however, if all of the
                         on a second – and larger – project comes as the  company’s plants proceed as currently scheduled
                         LNG industry is struggling to absorb a global  given the scepticism over the potential for new
                         oversupply amid low demand. Indeed, Reuters  projects to enter the market in the medium term.™

       Week 24   19•June•2020                   www. NEWSBASE .com                                             P13
   8   9   10   11   12   13   14   15   16   17   18