GLNG                                          COMMENTARY                                               GLNG










































       Germany eyes fourth highest global





       LNG import capacity by 2030






       Germany was formerly the biggest market for Russian pipeline gas in Europe.


        GERMANY          GERMANY is planning to top 70mn tonnes per   With floating storage regasification units
                         year (tpy) of liquefied natural gas (LNG) import  (FSRUs) typically taking as little as 18 to 24
       WHAT:             capacity by the end of the decade, Argus Media  months to construct, Germany has earmarked
       Germany is seeking to   reports citing documents from the German eco-  funds to build 10 FSRUs. Two will be located
       surpass 70mn tpy of peak   nomic ministry (BMWK) and planning applica-  at Wilhelmshaven, one at Brunsbuettel, one at
       LNG import capacity by   tions from German multinational energy utility  Stade, and Lubmin will host six, which could
       2030.             RWE. The ambitious target would represent  make it the biggest LNG import cluster on the
                         a more than twofold increase from its current  continent.
       WHY:              import capacity and catapult it into fourth spot   Following the passing of the LNG Accelera-
       Having previously relied   globally, trailing only China, Japan and South  tion Act, Germany heralded a new era for infra-
       on Russia for over 50%   Korea.                        structure construction projects with policies
       of its gas, Germany has   For decades Germany had been dependent  streamlined to turbocharge construction. As
       pivoted quickly to LNG to   on cheap Russian gas. In 2021, it sourced from  a result, Germany was able to bring the Hoegh
       fill its supply gap.  Russia around 55% of the 96bn cubic metres it  Esperanza FLNG terminal at the port of Wil-
                         consumed. But following Russia’s invasion of  helmshaven online in December, just eight
       WHAT NEXT:        Ukraine Germany sought to wean itself off Rus-  months after work began on the project.
       With several      sian gas as soon as possible and immediately   In addition to the 5.8mm tpy Wilhelmshaven
       neighbouring countries   embraced floating LNG (FLNG) terminals for  facility, a 3.5mn tpy FSRU facility has also already
       landlocked, Germany   their speed of construction as the best near-term  come online at the port of Lubmin. Meanwhile,
       could emerge as an LNG   solution. In the meantime, it also kept an eye on  the 3.1mn tpy Elbehafen FLNG terminal in
       hub for the region. It also   the long term with the development of onshore  Brunsbuettel received its first LNG cargo from
       plans to use the terminals   terminals at Stade, Brunsbuettel and Wilhelms-  Abu Dhabi National Oil Company (ADNOC) in
       as green hydrogen hubs   haven, which are all slated to come online before  mid-February.
       later.            2030.                                  And before the end of the  year,