       First LNG exports from Mexico’s Altamira site



       coming this summer, says New Fortress





        MEXICO           FIRST LNG from a floating liquefied natural   However, the current timeline marks a delay
                         gas production (FLNG) unit offshore Altamira,  from initial plans, in which New Fortress had
       The first two trains are   Mexico is expected to be achieved in July, man-  hoped to finish construction on the first FLNG
       80% finished.     agement at New Fortress Energy revealed on  unit in March.
                         February 28.                           The two FLNG units to be located offshore
                           The construction of the first of two “Fast  Altamira are among the five FLNG units New
                         LNG” (FLNG) liquefiers is about 80% finished.  Fortress is developing. The company also plans
                         The two liquefiers will possess a liquefaction  to install one unit at the Pemex-operated Lakach
                         capacity of 1.4mn tonnes per year (tpy). New  offshore gas field in the Gulf of Mexico about 90
                         Fortress is expected to source gas from the  km from the Port of Veracruz in south-eastern
                         United States taking advantage of spare capacity  Mexico. New Fortress also plans to install two
                         on the 2.6bn cubic feet (74.6mn cubic metres )  units to offshore Louisiana.
                         per day Sur de Texas-Tuxpan pipeline and then   “As we add liquefaction capacity and corre-
                         liquefy the gas for re-export.       sponding LNG supply to our portfolio, we intend
                           Upon completion of construction slated for  to sign long-term customer offtake agreements
                         May, the first FLNG unit will then set sail in June  that generate strong operating margins and sus-
                         for Altamira, with the first LNG achieved in July.  tainable cash flows,” management said during a
                         In August commercial in-service is expected to  fourth-quarter earnings call.
                         begin.                                 New Fortress generated $546.4mn of reve-
                           “We’re less than 100 days away from our  nue in the fourth quarter, a drop from $649mn
                         first FLNG setting sale to its home in Altamira,  during the same period of 2021. However, total
                         Mexico,” said chief financial officer Chris-  revenue for 2022 climbed to $2.37bn in 2022, up
                         topher Guinta during NFE’s fourth quarter  from $1.32bn in 2021. Net income for the fourth
                         2022 earnings call. “With construction near-  quarter of 2022 was reported as $66mn (31 cents
                         ing completion, we’re focused on installation,  per share), which marked a drop from $151mn
                         commissioning and operational readiness,” he  (73 cents per share) during the fourth quarter of
                         added.                               2021. ™