       Freeport LNG targets restart in




       early October




        PROJECTS         FREEPORT LNG, the owner and operator of a  liquefaction operations,” she said.
                         gas liquefaction plant and LNG export terminal   PHMSA had announced on June 30 that it
                         on Quintana Island on the Texas coast, has said  expected Freeport LNG to carry out several cor-
                         it is on track to resume partial operations early in  rective actions before bringing its facility back
                         the fourth quarter of this year.     on stream. These include: providing weekly
                           A spokeswoman for the company said in  updates on the density and temperature of the
                         a statement emailed to LNG Prime that early  LNG stored in its tanks; selecting one or more
                         October was the target date for restarting gas  independent third parties to perform certain
                         liquefaction. “Currently, it is estimated that the  assessments and evaluations; within 60 days of
                         resumption of partial liquefaction operations  the order’s issue, submitting a complete plan and
                         will be early October 2022,” she commented.  schedule for inspection to determine the extent
                           The spokeswoman confirmed that Freeport  of the damage caused by the fire and explosion
                         LNG was still aiming to resume operations  on June 8; and then responding appropriately
                         at full steam by the end of the year but did not  to corrective measures prescribed by PHMSA
                         say exactly how much capacity it might be able  after the receipt and analysis of data during this
                         to bring back online in the initial stages. “With  process.
                         commencement of such operations, we expect to   Freeport LNG has already launched its own
                         be able to deliver substantially all baseload pro-  “comprehensive review” of the incident with a
                         duction volumes,” she stated.        view to identifying problems and taking correc-
                           Freeport LNG had said in late June that it  tive action, the spokeswoman said in the state-
                         hoped to resume partial operations in about 90  ment sent to LNG Prime.
                         days, so early October would represent a slight   The fire and explosion on June 8 have acted
                         delay. The spokeswoman did not comment on  as a significant constraint on US LNG export
                         any changes in timing, but she did stress that  capacity. Freeport LNG is one of seven LNG
                         the company was working to ensure full com-  export terminals in the country, and its three
                         pliance with an order issued by the US Pipeline  production trains have a combined capacity
                         and Hazardous Materials Safety Administration  of 15mn tonnes per year (tpy). If the company
                         (PHMSA).                             goes ahead with proposals for adding a fourth
                           “Since the incident on June 8, the company  train, its total capacity would rise to 20mn tpy.
                         has worked collaboratively with all local, state  However, it has not yet made a final investment
                         and federal officials regarding the incident  decision (FID).™
                         response, investigation and safe resumption of






































       Week 27   08•July•2022                   www. NEWSBASE .com                                              P7
   2   3   4   5   6   7   8   9   10   11   12