       China’s CPP advances pipeline work in




       Bangladesh, completes project in Pakistan





        PIPELINES &      CHINA  Petroleum Pipeline Engineering  for the installation of a single point mooring
        TRANSPORT        Company (CPP) has recently reported pro-  system with 220-km double pipelines, including
                         gress with work on two pipeline projects in  the construction of a 146-km offshore pipeline
                         Southern Asia.                       and a 74-km onshore pipeline to carry up to 9mn
                           CPP, a subsidiary of China National Petro-  tonnes per year (tpy) from offshore to a refinery
                         leum Corp. (CNPC), has completed laying 100  at Chittagong. Once the project is in operation,
                         km of subsea pipeline work using an innovative  it will enable tankers over 100,000 DWT that
                         trencher that will enable the country to unload  cannot dock in Chittagong to unload at ports   The Pakistani
                         oil shipments. In Pakistan, the Chinese com-  elsewhere in the country.
                         pany finished the MFM MoGas project, which   The project is reported by Chinese media   branch of CPP
                         includes pipelines and storage facilities.  to be a part of China’s Belt and Road Initiative
                           A multi-functional modular seabed trencher  (BRI).                       announced last
                         developed by CPP has been used to dig a trench   The Pakistani branch of CPP announced last
                         11 metres deep to lay pipeline so as to not inter-  week that it had completed a total of nine pro-  week that it had
                         fere with shipping in shallow waterways near  jects in the country since 2017, the latest being   completed a total
                         Bangladesh’s main seaport of Chittagong. “The  the Mahmood Kot-Faisalabad-Machike (MFM)
                         installation of the marine pipeline is Bangla-  Pipeline Phase II reconstruction and expansion   of nine projects
                         desh’s first marine pipeline project; [it] needs  project, which include the TS-3 and TS-4 sta-
                         to complete six directional drillings and reach a  tions located in Faisalabad and Sheikhupura.  in the country
                         buried depth of 11 metres to avoid the commer-  TS-3 includes a single gasoline storage tank
                         cial and naval waterways, making the unprece-  with a 15,000 cubic metre capacity, and a fire   since 2017.
                         dented difficulty in the history of world marine  water-storage tank, while TS-4 includes two
                         engineering,” CPP said, according to China’s  gasoline storage tanks each with a 15,000 cubic
                         Global Times news agency.            metre capacity, and a fire water-storage tank.
                           Subsea trenches are usually 1.5-3.0 metres  Both sites include related supporting facilities,
                         deep. Digging a trench 5 metres deep is consid-  according to Pakistani PR firm Gwadar Pro.
                         ered difficult.                        The project is part of the 2,000-km pipeline
                           In December 2016, Bangladesh awarded  fuel transportation system owned and operated
                         CPP with an engineering, procurement, con-  by Pak-Arab Refinery Co. (PARCO). The system
                         struction and commissioning (EPCC) contract  runs between Karachi and Lahore.™



       P8                                       www. NEWSBASE .com                           Week 24   17•June•2022