       Dana Gas wins Iran




       gas arbitration case




        UAE/IRAN         UAE-BASED Dana Gas this week announced  described as “a much larger claim”. The final
                         that it had been awarded $607.5mn in damages  hearing is to be held in Paris in October 2022,
                         by an international arbitration tribunal relating  with a final announcement on the award of dam-
                         to a dispute with the National Iranian Oil Co.  ages anticipated in 2023.
                         (NIOC).                                Dana said that it would provide further
                           A 25-year gas sales and purchase contract  updates on the collection of the awarded sum in
                         (GSPC) was signed between NIOC and Dana  due course with the $607.5mn damages expected
                         affiliate Crescent Petroleum in 2005 for the UAE  to “significantly bolster” the company’s balance
                         Gas Project, which was intended to provide gas  sheet.
                         supplies to Crescent beginning in December   Meanwhile, Dana and Crescent, which are
                         2005, but no volumes were ever received, accord-  the joint operators of the Pearl Petroleum con-
                         ing to Dana.                         sortium in the Kurdistan region of northern
                           “The company has been updated by Cres-  Iraq, are working to add another 250mn cubic
                         cent Petroleum regarding the issuing of the final  feet (7.1mn cubic metres) per day of gas from the
                         award for damages in the first arbitration against  Khor Mor gas field by 2023 under the KM250
                         NIOC which was commenced in 2009, pursuant  expansion project.
                         to which a liability award was already made in   A further expansion is planned under the
                         2014,” it said.                      KM500 project but sign-off on this project is
                           Dana noted that this concludes the first arbi-  dependent on reaching an agreement with
                         tration case, covering the first 8.5 years of the  an offtaker. Talks are reported to be ongoing
                         GSPC from 2005 to 2014. A second arbitration  regarding extending the Kurdistan region’s pipe-
                         is ongoing relating to the remaining 16.5 years  line network into Turkey or into Federal Iraqi
                         of the contract from 2014 to 2030, which Dana  territory.™