Page 6 - MEOG Week 28 2022
P. 6

MEOG                                   PIPELINES & TRANSPORT                                           MEOG


       Iraq struggles to expand Gulf export capacity





        IRAQ             IRAQ’S efforts to expand oil export capacity via  the key obstacle to expanding capacity, describ-
                         its southern ports are being hampered by issues  ing the subsea pipelines that link to ABOT’s
                         with upgrading pumping facilities on the pipe-  offshore single-point moorings (SPMs) as old,
                         lines that feed its main oil terminal.  costly and a “very, very sensitive element of our
                           Basra Oil Co. (BOC) – a subsidiary of the  export capacity”.
                         state-owned Iraqi National Oil Co. (INOC) –   Allawi said: “I don’t think we’ll be expanding
                         had been hoping to raise the export capacity at  our capacity beyond … another 1mn bpd within
                         the Al-Basrah Oil Terminal (ABOT) by around  five years.” He later clarified that the 6mn bpd
                         150,000 barrels per day (bpd) during Q2, but  figure was what he thought was “realistically”
                         delays improving flows to the facility have  achievable by Iraq during that timeframe.
                         pushed the completion date back. ABOT has a   BOC is also working to rehabilitate two pipe-
                         current capacity of 3.5mn bpd, which Iraq uses  lines that feed the nearby Khor al-Amaya Oil
                         almost in its entirety.              Terminal (KAAOT). Ruptures in the conduits
                           A local industry source was quoted by Reu-  forced the terminal to go offline in 2017 and
                         ters as saying this week that infrastructure allows  only return to operations briefly in the interven-
                         for exports of just 3.3mn bpd from ABOT, but  ing period.
                         BOC had hoped to figure this figure to 3.45mn   A contractor has been hired to find and repair
                         bpd by the end of June. This has now been  the fault, while a third pipe is to be installed, aim-
                         revised to 3.35mn bpd in August and 3.45mn  ing to resume exports from KAAOT’s SPMs by
                         bpd. However, the source said: “I’m not sure if  the end of 2023. When operations resume, the
                         BOC can meet this deadline due to the delay in  terminal is anticipated to operate at around
                         the [pumping stations] project.”     400,000 bpd, down from its 600,000 bpd capacity
                           The doubts come amid uncertainty about  prior to going offline.
                         Iraq’s ability to achieve upstream expansion   In March, BOC said that the pipeline over-
                         from within the country’s government. While  haul is part of efforts to increase crude export
                         Oil Minister Ihsan Abdul Jabbar has set tar-  capacity from the southern ports to 6mn bpd by
                         gets for oil production that have changed on an  2026. This will include the laying of two 48-inch
                         almost quarterly basis, Deputy Prime Minister  (1,066-mm) pipelines as well as the construction
                         Ali Allawi, who is also Iraq’s Finance Minister,  and installation of new single-point mooring
                         said last month that the ambition of adding 3mn  (SPM) facilities, with BOC preparing a tender
                         bpd of output capacity by 2027 is not realistic.  worth around $1bn that will be opened up to
                           He highlighted severe export constraints as  international companies.™












































       P6                                       www. NEWSBASE .com                           Week 28   13•July•2022
   1   2   3   4   5   6   7   8   9   10   11