Page 11 - GLNG Week 10 2021
P. 11

GLNG                                           AMERICAS                                               GLNG








































       Chilean company set to take delivery of




       tugboats for LNG terminal in El Salvador





        PROJECTS &       SAAM Towage of Chile said earlier this week  comply with the top category of Bureau Veritas’
        COMPANIES        that it was preparing to take delivery of two new  escort and firefighting standards, it added.
                         tugboats that will be used at an LNG terminal in   SAAM Towage did not comment on the value
                         El Salvador’s Acajutla port.         or terms of the contract. It did, however, quote
                           In a statement, SAAM Towage said that its  technical manager Pablo Cáceres as saying he
                         contractor, the Turkish shipbuilding company  was glad that the tugboats could be completed,
                         Uzmar, had recently completed the two ships,  even though the coronavirus (COVID-19) pan-
                         which will be known as SAAM Centzunat and  demic has not yet died down.   The company has
                         SAAM Acaxual. Both of the RAstar 3200W ves-  “The project was a success, despite the pan-
                         sels will go into operation at the Acajutla termi-  demic’s particular complications, which we   said it expects
                         nal that Energía del Pacífico (EDP) is building,  were able to navigate together, while staying on
                         it noted.                            schedule and in concordance with the previously   to invest about
                           It will be more than a month before the boats  agreed conditions,” he commented. “It was an
                         begin regular service. They are due to depart  enormous challenge. Completing it successfully  $1bn in the LNG
                         from the Turkish port of Izmit on March 12  will help us provide the best service to Energía   project in El
                         and will be at sea for 40 days before arriving at  del Pacífico.”
                         Acajutla.                              The company has said it expects to invest   Salvador.
                           The Chilean company went on to say that the  about $1bn in the LNG project in El Salvador. It
                         tugboats had been specially designed by Robert  will use these funds to install or build a floating
                         Allan Ltd (Canada), to meet EDP’s needs at the  storage and regasification unit (FSRU) offshore
                         Acajutla terminal. The vessels are 32 metres long  Ajacutla, a gas-fired thermal power plant (TPP)
                         and have a bollard pull of more than 80 tonnes, it  with a generating capacity of 378 MW and a
                         stated. They have a top speed of more than 13.5  44-km double-circuit power transmission line
                         knots, and each has been outfitted with Kongs-  that will tie the TPP into the Central American
                         berg US255 FP azimuth thrusters and two CAT  Electrical Interconnection System (CAEIS).
                         3516C 2,350-kW engines, it said.     Additionally, it has hired Boskalis (Netherlands)
                           Additionally, it said, the boats were built to  to build a subsea pipeline connecting the FSRU
                         meet the highest safety standards for LNG ter-  to the power station and Elecnor (Spain) to engi-
                         minal operations, as specified by the buyer. Their  neer and build the 230-kV power cable and all
                         equipment, design features and construction  associated substations.™



       Week 10   12•March•2021                  www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14   15   16