Page 11 - GLNG Week 49 2022
P. 11

GLNG                                           AMERICAS                                               GLNG




       Freeport LNG again delays





       restart of an export





       facility to end of year





        EXPORTS         FREEPORT LNG has again delayed the restart  release.
                        of the US’s second-largest liquefied natural gas   Each of Freeport LNG’s three liquefaction
                        (LNG) export facility to the end of December. It  trains will be restarted and ramped up safely, in
                        was to have opened in mid-December.  a slow and deliberate manner, with each train
                          The plant was closed on June 8 following an  starting separately before restarting a subsequent
                        explosion and fire. The company has several  train. It is expected that approximately 2bn cubic
                        times predicted start-up dates then missed them.  feet (56.6mn cubic metres) per day of produc-
                          “Based upon current progress, and subject  tion will be achieved in January 2023, the com-
                        to us continuing to meet necessary regulatory  pany said in November. Full production utilising
                        requirements, we now anticipate that the restart  both docks remains anticipated to commence in
                        of our liquefaction facility will be achieved  March 2023, said Freeport LNG last month.
                        around year end,” Freeport LNG spokesperson   But energy consultancy Energy Group direc-
                        Heather Browne said to Reuters in an email.  tor Alex Munton told Reuters that gas process-
                          Proposed remedial work activities for a safe  ing at Freeport would likely not restart until the
                        restart of initial operations have been submitted  first quarter of next year, “with longer delays
                        to the relevant regulatory agencies for review and  possible.”
                        approval, the company said in mid-November.  In November, the Pipeline and Hazardous
                          As of November 14, the reconstruction work  Materials Safety Administration issued a report
                        necessary to commence initial operations,  on the June explosion saying that the export
                        including use of all three liquefaction trains,  terminal faced inadequate operating and test-
                        two LNG storage tanks and one dock, had been  ing procedures. Human error and fatigue were
                        approximately 90% complete, with all recon-  also to blame, said the federal pipeline safety
                        struction work anticipated to be finished by the  agency.™
                        end of November, the company said in a press






































       Week 49  08•December•2022                www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14   15   16