NorthAmOil                                   COMMENTARY                                          NorthAmOil


                                                                                                  Sempra and its partners
                                                                                                  are advancing plans to
                                                                                                  expand Cameron LNG.

























                         Cameron expansion                    more rapidly than ever before on securing offtak-
                         As NFE awaits its necessary regulatory approv-  ers for its proposed Rio Grande LNG facility in
                         als offshore Louisiana, LNG plans are being  Texas.
                         advanced onshore in the state as well. The part-  The company announced on April 6 that
                         ners in the Sempra-led Cameron LNG terminal  it had entered into an SPA with a subsidiary
                         have entered into a heads of agreement (HoA) on  of China’s ENN Natural Gas for the supply of
                         Phase 2 of the project.              1.5mn tpy from Rio Grande over a 20-year
                           Under the HoA, affiliates of Sempra, TotalEn-  period.
                         ergies, Mitsui & Co. and Japan LNG Invest-  Notably, this is the second deal in two weeks
                         ment – a joint venture between Mitsubishi  for both companies. On March 24, NextDec-
                         and Nippon Yusen Kabushiki Kaisha (NYK) –  ade entered into a binding HoA with China’s
                         would add a fourth train at Cameron, as well as  Guangdong Energy Group Natural Gas, also for
                         increasing capacity of the existing three trains  the supply of up to 1.5mn tpy from Rio Grande
                         through debottlenecking activities.  over a 20-year period. And on March 29, Energy
                           The HoA would see Sempra Infrastructure  Transfer said it had entered into two SPAs with
                         being allocated a 50.2% of the fourth train’s pro-  affiliates of ENN for 1.8mn tpy and 900,000 tpy
                         duction capacity and 25% of projected debot-  of LNG over 20 years from its proposed Lake
                         tlenecking capacity under tolling agreements.  Charles LNG export terminal.
                         The remaining capacity would be allocated   “The commercial momentum at [Rio Grande
                         equally among Cameron LNG’s existing Phase  LNG] is accelerating and we believe the com-
                         1 customers. Sempra intends to sell the LNG  pany is well placed to benefit from the strength-
                         corresponding to its capacity under long-term  ening LNG market,” stated NextDecade’s
                         sale and purchase agreements (SPAs) prior to  chairman and CEO, Matt Schatzman.
                         taking an FID on Phase 2 of Cameron, it said.  Indeed, prior to the past two weeks, Next- The offtake deals
                           The fourth train would have a capacity of  Decade only had one other offtaker lined up
                         6.75mn tpy. Cameron LNG’s existing trains have  for Rio Grande LNG, so recent developments   involving Chinese
                         a capacity of 4.5mn tpy each, but this now looks  represent significant momentum for the com-  companies
                         set to be expanded. However, Sempra cautioned  pany. It is aiming to take an FID on at least two
                         that the HoA was non-binding and a number  trains at Rio Grande in the second half of 2022,   illustrate that
                         of steps still needed to be taken and permits  sanctioning its remaining three trains at some
                         needed to be obtained prior to each of the Cam-  point thereafter, and first production is targeted   Europe is not
                         eron LNG partners agreeing to an FID.  from 2026.
                           Sempra also said that Cameron LNG had                                   alone in seeking
                         awarded two front-end engineering and design  What next?                   more US LNG.
                         (FEED) contracts to Bechtel Energy and a joint  The offtake deals involving Chinese companies
                         venture between JGC America and Zachry  illustrate that Europe is not alone in seeking
                         Industrial.                          more US LNG, and that buyers elsewhere in the
                           “At the conclusion of this competitive FEED  world will be all too aware of competition for
                         process, one contractor is expected to be  supplies intensifying.
                         selected to be the engineering, procurement and   If this pace of developments continues – or
                         construction (EPC) contractor for the project,”  even picks up – more announcements on offtake
                         Sempra said.                         agreements, FIDs, various regulatory steps and
                                                              other moves to advance the next wave of US liq-
                         Another supply agreement             uefaction projects can be expected in the com-
                         Meanwhile, NextDecade appears to be moving  ing weeks and months.™