Page 13 - AfrOil Week 27 2021
P. 13

AfrOil                                           POLICY                                                AfrOil



                         Joanne Bate, the COO of IDC, also expressed   industry. We are looking forward to working
                         optimism. “The development of the hydrogen   together with Sasol in identifying and co-devel-
                         industry is a key enabler in South Africa’s just   oping such catalytic projects. Our involvement
                         transition to a decarbonised future,” she com-  in the development of the hydrogen industry
                         mented. “Hydrogen has the potential to decar-  also provides opportunities to fulfil our devel-
                         bonise various industrial sectors. IDC intends   opment mandate, which entails job creation
                         on getting involved in the development of those   and opportunities to involve previously disad-
                         catalytic projects needed to develop this new   vantaged entities.” ™



                                             PROJECTS & COMPANIES
       Slight delay for first gas from GTA






        MAURITANIA/SENEGAL  BP (UK) has pushed the target date for starting   progress during the quarter, with key mile-
                         production at Grand Tortue/Ahmeyim, an off-  stones achieved across all major workstreams,”
                         shore natural gas-bearing block that straddles   commented Andrew G Inglis, the chairman
                         the maritime border between Mauritania and   and CEO of Kosmos. “However, we are seeing
                         Senegal, back to the third quarter of 2023.  cost inflation and supplier delays in the current
                           US-based Kosmos Energy, a non-operating   environment together with some scope growth,
                         partner in the project, announced the delay ear-  and as a result, we are updating our estimates,
                         lier this week. In a statement, it said that BP had   with first gas now expected in the third quarter
                         changed the schedule in line with information   of 2023.”
                         from TechnipFMC, the international oilfield   GTA is an ultra-deepwater block that lies
                         services provider that is serving as the engineer-  athwart the maritime border between Maurita-
                         ing, procurement, construction, installation and   nia and Senegal. It was discovered by US-based
                         commissioning (EPCIC) contractor at GTA.  Kosmos Energy in 2015 and is believed to hold
                           TechnipFMC explained the need for delay   some 15 trillion cubic feet (425bn cubic metres)
                         by pointing out that the Chinese shipyard that   of natural gas. BP joined the project in 2016,
                         is building a floating production, storage and   and the two companies made a final investment
                         off-loading (FPSO) vessel for installation at the   decision (FID) on first-phase production in late
                         block had fallen behind schedule, Kosmos said.   2018.
                         The shipyard, which is owned by a division of   The partners intend to use gas from the
                         China Ocean Shipping Co. (COSCO), is report-  licence area to support an LNG project. To this
                         edly experiencing labour shortages because of   end, they have contracted Bermuda-registered
                         the uptick in economic activity that has followed   Golar LNG to convert the Gimi LNG tanker into
                         the ebbing of the coronavirus (COVID-19) pan-  a floating LNG (FLNG) plant with a production
                         demic. As a result, it will not be able to deliver   capacity of 2.5mn tonnes per year (tpy). The
                         the FPSO by the previously agreed deadline,   FLNG unit will process gas delivered via pipe-
                         and BP and Kosmos will have to wait to start   line from the FPSO. ™
                         production.
                           These developments are not expected to
                         cause major delays. GTA should begin yielding
                         gas only about three months later than antici-
                         pated, Kosmos said. The company also noted,
                         though, that the change of schedule would cause
                         the cost of the project to rise. The budget for the
                         first phase of work at the block is on track to go
                         up by $100mn, it stated.
                           In the meantime, BP and Kosmos are mak-
                         ing progress in other areas. They are on track to
                         close the FPSO sale and lease-back transaction
                         before the end of September 2021 and will then
                         focus on efforts to refinance the loans that the
                         national oil companies (NOCs) of Senegal and
                         Mauritania took out to finance their share of
                         project costs. Additionally, they are working to
                         draw up plans for the second phase of the project
                         and hope to make a final investment decision
                         (FID) in late 2022, as previously announced.
                           “In Mauritania and Senegal, the Grand Tor-
                         tue/Ahmeyim project continued to make steady   GTA contains 425 bcm of gas (Image: Kosmos Energy)



       Week 27   07•July•2021                   www. NEWSBASE .com                                             P13
   8   9   10   11   12   13   14   15   16   17   18