Page 12 - AsianOil Week 36
P. 12

AsianOil                                         OCEANIA                                             AsianOil




       Restart troubles for





       Australian LNG facilities






       Attempts to restart Prelude FLNG and the second train at Gorgon
       are running into obstacles and taking longer than initially expected




        COMMENTARY       ATTEMPTS to restart the second train at Gor-  super-major discovered cracks in the kettles dur-
                         gon LNG and the Prelude floating LNG (FLNG)  ing routine maintenance on the train that began
                         facility – liquefaction capacity that has been  in May and was subsequently extended to carry
       WHAT:             offline in Australia – are running into obstacles.  out the necessary repairs.
       Chevron and Shell   The challenges illustrate the complexity of the   Chevron had initially anticipated completing
       have separately run   projects involved, and while operators Chevron  the repairs and returning Train 2 to service in
       into challenges as   and Royal Dutch Shell have sought to downplay  September, but now says it expects the facility to
       they attempt to bring   the setbacks, more issues cannot be ruled out  be restarted in October.
       liquefaction facilities in   before the facilities are back online.  The company said that following its ongo-
       Australia back online.  While the ongoing outages represent a set-  ing technical work, it was further refining its
                         back to the facilities’ operators, however, the  approach and had decided that some welds in
       WHY:              broader industry may welcome them as it  targeted areas would require additional work.
       More time is needed   struggles with the global glut of LNG, which is  This comes after the Australian Manufacturing
       to bring Gorgon Train 2   still being exacerbated by new capacity coming  Workers Union said in July that cracks up to 1
       back online, while an   online in the US.              metre long and 30mm deep were found on 8-11
       attempted restart of                                   kettles on Train 2. The trade union raised con-
       Prelude is reported to   Extra time                    cerns that the heat exchangers would need to
       have failed.      On September 3, Chevron Australia said it  be replaced altogether, so while the repairs are
                         would require extra time to complete repairs of  more extensive than Chevron initially expected,
       WHAT NEXT:        propane heat exchangers – or kettles – on Train  it appears that this is not the worst-case scenario.
       The ongoing outages   2 at the Gorgon terminal on Barrow Island, off   However, there has been speculation that
       may be welcomed   the northwest coast of Western Australia. The  welding  work  on  the  cracks  was  initially
       by the industry as it
       struggles with global LNG
       oversupply.






























                         The Gorgon LNG facility in WA.



       P12                                      www. NEWSBASE .com                      Week 36   10•September•2020
   7   8   9   10   11   12   13   14   15   16   17