Page 12 - DMEA Week 15 2021
P. 12

DMEA                                            REFINING                                               DMEA


       Early operations to begin




       at Al-Zour in November




        MIDDLE EAST      KUWAIT’S  615,000-barrel per day (bpd)  Covid-19 and restricted travel into the country
                         Al-Zour refinery is tabbed to begin first refining  in early February.
                         operations in November having reached 97.83%   Test runs are understood to be ongoing,
                         completion as of the end of February.  while oil feedstock began flowing to the refinery
                           The progress was announced by the country’s  through a dedicated pipeline on December 1.
                         Minister of Oil and Minister of Higher Educa-  The project dovetails with the Clean Fuels
                         tion Dr Muhammad Al-Fares in a statement to  Project (CFP), which comprises of the upgrade
                         press. He explained that the first mini refining  and expansion of the two existing refineries at
                         unit will begin operations in November, as it  Mina Abdullah and Mina al-Ahmadi to a com-
                         gradually ramps up ahead of being fully opera-  bined capacity of 800,000 bpd. A 264,000-bpd
                         tional at the end of Q1 2022.        crude distillation unit (CDU) was brought
                           The project, which once commissioned, will  on-stream at Mina Abdullah in December.
                         be the Middle East’s largest refinery to have been   Al-Fares said that a biofuel project is being
                         built in a single stage, is a key part of the emirate’s  gradually implemented at both refineries with
                         plans to expand its downstream capabilities.  the combined completion rate of the facilities
                           The refinery at the southern port of Al-Zour  having reached 99.29%. He noted that while all
                         is being developed by Kuwait Integrated Petro-  units at Mina Al-Ahmadi have been completed,
                         leum Industries Co. (KIPIC), a subsidiary of  work is still ongoing at several units at Mina
                         state oil firm Kuwait Petroleum Corp. (KPC).  Abdullah with completion now anticipated in
                           KIPIC had set a target commissioning date of  July.
                         late 2020, pushing this back to Q1 2021 as restric-  The CFP and Al-Zour projects are estimated
                         tions relating to Covid-19 slowed progress.  to cost $15.7bn and $16.1bn respectively, with
                           Several services firms and contractors  the latter figure including the cost of associated
                         involved in the development of Al-Zour were  LNG facilities.
                         reported to have attempted to invoke force   Downstream-focused Kuwait National
                         majeure with restrictions having made it impos-  Petroleum Co. (KNPC) has plans in place to
                         sible to meet deadlines, while Kuwait recently  more than double its refining capacity to 2mn
                         re-introduced measures to halt the spread of  bpd by 2035 under a $25bn plan.™












































       P12                                      www. NEWSBASE .com                           Week 15   15•April•2021
   7   8   9   10   11   12   13   14   15   16   17