Page 7 - AfrOil Week 03 2022
P. 7

AfrOil                                       COMMENTARY                                                AfrOil


                         However, according to correspondence between   2021, with local outlet Modern Ghana reporting
                         the company and the Electricity Company of   in August that refinery staff had “recently locked
                         Ghana at the time, Sentuo had requested the   up some management staff”.
                         relocation of two electricity pylons and was due   Meanwhile, state utility ECG said in Decem-
                         to pay $190,000 for the work.        ber that it had cut electricity supplies to TOR fol-
                           Local news reports showed ongoing land   lowing the facility’s failure to pay $4.3mn of debt.
                         clearing work, which Tema Development Corp.   “We’ve pursued [TOR] for some time to pay
                         (TDC) said was limited to the construction of   the bill, but unfortunately, all our [efforts were]
                         a wall.                              not yielding, so we were compelled to cut the
                           Speaking at a dinner in Accra on Janu-  lines,” according to the leader of a taskforce set
                         ary 13, the EPA’s acting director of petroleum   up to recover the missing payment.
                         Kojo Agbenor-Efunam said that the agency’s   He added that ECG would restore power
                         environmental impact assessment (EIA) also   only if the state refinery pays at least 30% of the
                         showed that the project site was “very close” to   debt. However, the local Joy News reported at
                         a residential area, reiterating the issues noted in   the time  that TOR had expressed surprise over
                         the second quarter of last year.     ECG’s actions.
                           “We saw that this is a refinery that you’re   The two companies held talks in ECG’s Accra
                         building about 15 metres from the nearest res-  offices regarding the repayment of debt, with Joy
                         idence. So it is like you are placing a bomb very   News quoting sources as saying that the parties
                         close to the people and any time something goes   had agreed on an $81,000 per month payment   Combined, the
                         wrong and there is a blast, you are going to wipe   plan, which was supposed to kick off this month,   completed Sentuo
                         out almost everybody,” he said.      with payments to be increased once TOR’s oper-
                           Agbenor-Efunam added that the building   ations ramp up in 2022.         plant and the
                         would also “close the buffer between the Tema   Combined, the completed Sentuo plant and
                         Industrial zone and the residential area.”  the rehabilitated TOR would be more than capa-  rehabilitated
                           The findings come following clarification   ble of catering to Ghana’s 80,000-90,000 bpd
                         that TDC had designated the location for   petroleum product demand. This is undoubt-  Tema refinery
                         industrial uses. “We were looking at the area as a   edly an attractive proposition for Accra, which   would be more
                         buffer, but the TDC said the area was not a buffer   last year moved to buy back offshore oil licences
                         but had been zoned for industrial purpose. So   to gain control over the sector’s performance.  than capable of
                         we had no choice,” he said.
                           “As far as we are concerned, the place is not   Gas plant               covering Ghana’s
                         suitable ... The planning authorities had given   Meanwhile, Energy Minister Matthew Opoku
                         the development permit to the company and   Prempeh has charged the board of Ghana   fuel demand
                         they have given them authorisation to clear the   National Gas Co. (GNGC) with ensuring the
                         land with or without EPA permit,” Agbenor-Efu-  establishment of a second processing plant for
                         nam said.                            the country.
                           With the EPA appearing not to have been   Speaking last week at the board’s first meet-
                         able to counter the site work, it is hard to argue   ing of the year, he commented that another gas
                         against public accusations of toothlessness   processing plant was long overdue, “especially
                         against the agency.                  as the population expands and over 70% of our
                                                              fuel requirement for power generation is met by
                         Existing facility                    natural gas.”
                         Tema is the location of Ghana’s only existing   Ghana currently has the capacity to produce
                         refinery, the struggling 45,000 bpd Tema Oil   over 350mn cubic feet (9.91mn cubic metres)
                         Refinery (TOR).                      per day of gas from two of its three oil and gas
                           The facility has been plagued by issues since   fields, the Jubilee and TEN fields, which produce
                         an explosion at its distillation unit in early   wet gas. Sankofa Gye Nyame, the most recent
                         2017 and was closed completely between July   field to be commissioned, produces dry gas. It is
                         2020 and January 2021. Outages have been   located 60 km offshore in the Tano basin.
                         experienced at the crude distillation and fluid   The Atuabo gas processing plant is, however,
                         catalytic cracking units, while only one of the   capable of processing less than half that amount.
                         CDU’s furnaces is currently operational, giving   As of October 2021, it was processing 130-140
                         the 56-year-old facility an effective throughput   mcf (3.68-3.96 mcm) per day of gas to for deliv-
                         capacity of 30,000 bpd.              ery to domestic electricity generation plants,
                           However, in May 2021 S&P Global Platts   primarily to the Aboadze thermal power plant
                         quoted sources as saying that the refinery had   (TPP).
                         depleted all of its feedstock, with operations   Consequently, this has restricted wet gas
                         halted for maintenance and repair works to   supplies to 130 mcf per day, equivalent to almost
                         begin.                               100% of the country’s entire installed gas pro-
                           “The refinery is currently down. We   cessing capacity. As with the refining issue, a
                         exhausted the crude oil we had and we are yet to   new gas processing plant is expected to elimi-
                         receive any new crude oil cargo,” the source said.   nating Ghana’s dependence on imports. In this
                         “In the meantime, the maintenance outfit of the   case, the shipments that would be affected are
                         company is taking advantage of the situation to   irregular supplies from Nigeria, which delivers
                         carry out some few repair works.”    gas to the Ghanaian market via the West African
                           Frustrations boiled during the second half of   Gas Pipeline (WAGP). ™



       Week 03   19•January•2022                www. NEWSBASE .com                                              P7
   2   3   4   5   6   7   8   9   10   11   12