Page 8 - FSUOGM Week 40 2021
P. 8

FSUOGM                                PIPELINES & TRANSPORT                                         FSUOGM


       Gazprom starts filling first




       Nord Stream 2 string




        EUROPE           RUSSIA’S Gazprom has begun filling the first  independent operator. Under an EU court ruling
                         string of the Nord Stream 2 pipeline with nat-  that Gazprom recently failed to get overturned
       Nord Stream 2 could   ural gas, ahead of its commercial launch, which  in a German court, however, doing so would
       help ease supply   Moscow has said should happen later this year.  violate the bloc's rules on the unbundling of gas
       constraints in Europe.  Gazprom announced that Nord Stream 2’s  transport infrastructure from supply. This could
                         construction had reached completion in early  mean Gazprom has to spin off Nord Stream 2,
                         September. It has since undergone pre-com-  which would likely result in delays that would
                         missioning activities to assure the pipeline’s  prevent the pipeline coming on stream this year
                         integrity, the Nord Stream 2 operating company,  as Russia hopes.
                         wholly-owned by Gazprom, said in a statement   Gas is now trading at above $1,100 per 1,000
                         on October 4.                        cubic metres on the European wholesale mar-
                           “This included the internal inspection by spe-  ket – an unprecedented height. There are fears of
                         cial devices, as well as external visual and instru-  a further increase and possible shortages in the
                         mental surveys of the pipeline,” Nord Stream 2  event of a cold winter. Gazprom has been blamed
                         said in a statement on October 4. The pipeline  for exacerbating the crisis by withholding some
                         is built and independently certified according to  supply, even though it has been sending more gas
                         applicable technical and industry standards to  this year than last.
                         ensure reliable and safe operations.”  A decision on Nord Stream 2’s certification
                           Nord Stream 2 could help ease supply con-  is likely to be made after a new government is
                         straints in Europe that have caused natural gas  formed in Germany following coalition talks.
                         prices to soar to record heights, undermining  The decision will be up to Germany’s regulator
                         the post-pandemic economic recovery. But first  but will be reviewed by the European Commis-
                         Nord Stream 2 will need to be certified as an  sion. ™



       Energinet warns of $157mn cost



       overrun at Baltic Pipe





        DENMARK          DANISH  gas grid operator Energinet has  Danish section is now projected to cost €1.1bn.
                         warned of a €135mn ($157mn) hike in costs   “We have been forced to revise the budget,
       Construction was halted   at the Danish section of the Baltic Pipe, caused  due to a number of unforeseen costs, not
       after an environmental   partly by issues with environmental permitting.  least stemming from the consequences of the
       permit was repealed.  Denmark’s environmental and food appeals  repealed environmental permit,” Energinet said.
                         board announced in June that it had repealed  “The temporary halt to construction has meant
                         a construction permit for Baltic Pipe’s onshore  a lot of extra claims from the contractors who
                         section, prompting concerns that the pipe-  were already working on the onshore pipeline at
                         line would not come online in October 2022  the time. We also have to acknowledge that the
                         as planned. The timing of its launch is key as  integration of Baltic Pipe into the existing Nybro
                         Poland, which is due to take most of its gas, wants  terminal is extremely complex and costly.”
                         to sever supply ties with Russia’s Gazprom at the   Despite these setbacks, Energinet still insisted
                         end of that year after its long-term contract runs  that the project was still a profitable venture,
                         out.                                 projecting it would save Danish gas consumers
                           Construction was halted after the permit was  €270mn in tariffs. At full capacity the pipeline
                         repealed, and neither Energinet nor Gaz-System,  will flow 10bn cubic metres per year of gas.
                         which operates Baltic Pipe’s Polish section, have   The government in Warsaw has said it wants
                         said when it might resume. Energinet is cur-  to fully substitute the gas supplies it currently
                         rently in the process of obtaining a new permit.  buys from Russia with volumes from Norway
                           The permitting issue alone added €80mn to  via Baltic Pipe, and LNG shipments.
                         Baltic Pipe’s cost in Denmark, Energinet said.   Permitting issues in Denmark were also one
                         Design changes to Baltic Pipe’s connection with  of the chief reasons for the delay of Russia’s Nord
                         Norwegian infrastructure and high demand for  Stream 2 pipeline beyond its scheduled launch
                         construction contractors were other contrib-  at the end of 2019. Poland vehemently opposes
                         uting factors, the operator said. As a result, the  that project. ™

       P8                                       www. NEWSBASE .com                        Week 40   06•October•2021
   3   4   5   6   7   8   9   10   11   12   13