Page 20 - LWFC Catalog
P. 20

With the necessary sample modifications, ASTM D2434 has proven to be an
                                         effective method for testing permeability of PLDCC. During a large project,
                                         buoyancy  questions  arose  prompting  the  development  of  methods  for
                                         testing natural saturated densities in-situ, resulting from water rising through
                                         PLDCC.  Measurements  of  natural  saturated  densities  were  conducted
                                         under levels of hydraulic head from 1’ – 10’. It was determined that a head
                                         of 1’ – 2’ is enough to establish representative saturated unit weights. Natural
                                         saturated density testing has been incorporated Castle Rock Consulting’s
                                         D2434 permeability testing.
     Wednesday                 4PM -  Rehabilitation of Mechanically Stabilized Earth Bridge Approach

         October              4:50 PM Embankments Using Geofoam Blocks: Hybrid Approach Embankment
                                         Concept The Northern Marmara Highway, total of 400 km long including all
              20                         the connections and belt routes, has recently been constructed in Turkey.
                                         The highway route goes through the industrious zones along the Northern
                                         Marmara Region and connects Tekirdag and Sakarya through Istanbul. The
                                         highway was built to reduce the traffic load on the existing transportation
                                         networks and to provide east – west transit transportation corridor which
                                         significantly  helped  to  relief  the  traffic  in  Istanbul.  The  eastern  portion  of
                                         the route called Region 6 which goes through soft soil sites where various
                                         geotechnologies were used to construct highway embankments. One of
                                         the overpasses in the Region 6 was constructed as two span bridge with
                                         44 m deep drilled shafts pile supported foundations. In addition, 22 m long
                                         1.0 m diameter deep mix columns were constructed with 2 m x 2 m grid
                                         to support the mechanically stabilized earth approach embankments to
                                         prevent both the bearing capacity and settlement failures. However, the
                                         improvement  zone  under  the  footprint  of  7.4  and  8.4  m  high  approach
                                         embankments was only kept within a limited zone of 30 m behind each
                                         abutment.    No  soil  improvement  techniques  were  implemented  in  the
                                         remaining  footprint  of  the  approach  embankments.  Mechanically
                                         stabilized  earth  approach  embankments  were  constructed  using  biaxial
                                         geogrid reinforcement with steel wire mesh facing which accommodates
                                         vegetative  soil  near  the  facing.  The  longitudinal  slopes  of  the  two  lane
                                         mechanically stabilized earth approach embankments were constructed
                                         with  7.1%  and  8.4%  which  was  quite  steep  and  created  driving  safety
                                         concerns.  Therefore,  the  rehabilitation  project  was  prepared  to  create
                                         approach embankments with 5.0% longitudinal slopes which required to
                                         construct additional fill atop the existing embankments. If the conventional
                                         earth  was  selected  to  construct  flatter  longitudinal  slope,  this  additional
                                         stress  increase  will  result  both  bearing  capacity,  total  and  differential
                                         settlement issues in the sections of the approach embankment where soil
                                         improvement was not implemented initially. A comprehensive subsurface
                                         investigation  program  including  SPT,  CPTU,  PMT  in-situ  and  laboratory
                                         testing program were carried out by the geotechnical consultant. Based
                                         on the subsurface profile, a portion of the existing mechanically stabilised
                                         earth approach embankments, where there is no soil improvement, were
                                         excavated in a stair-step fashion to satisfy the allowable bearing capacity
                                         and settlement criteria. Then, the remaining sections were constructed using
                                         geofoam  blocks  without  imposing  additional  stress  increase.  Geofoam
                                         block  technology  successfully  implemented  in  thisrehabilitation  project
                                         and set a hybrid embankment model where two geotechnologies can be
                                         utilised in transportation infrastructure.
   15   16   17   18   19   20   21   22   23   24   25