INTERNAL PHASING: WEEKLY SEQUENCING



                    th
            W/C 11 May - Create new Quiet room within PDR space & 1 to 1 room
            Erect temporary hoarding, Isolate and remove existing lighting and small power. Strip down existing s/ceilings and build new
            partitions, form new doorways, once completed remove temporary hoarding. Following the removal of the hoarding M&E and
            IT commences including stripping out all plumbing within Medical Room. Install new s/ceilings once area is clear of all trades.
            Complete M&E works and IT, install new doors, complete decoration work and lay new flooring once clear.
            Furniture move on completion

                        th
            Monday 11 May
            Please Note: Isolate and remove services to allow a temporary door to be formed in General Office/BOH wall – this will allow
            access to the General Office throughout the duration of office disruptions


            W/C 18 May -New General Office
                    th
            Erect temporary hoarding, Isolate and remove existing lighting small power and IT services. Strip down existing s/ceilings and
            partition wall. Build new partitions and new doorways, once completed remove temp hoarding. M&E and IT will then
            commence along with installation of new s/ceilings, complete M&E works and IT, then install new doors. Carryout decoration
            work and lay new flooring once clear.
            Furniture move on completion


            W/C 25 May - New BM Office
                    th
            Erect temporary hoarding, Isolate and remove existing lighting, small power and IT. Strip down existing s/ceilings and build new
            partitions, form new doorways, once completed remove temp hoarding. M&E and IT work will then commence working in
            tandem with the installation of new s/ceiling. Complete M&E works and IT then install new doors, complete decoration work
            and lay new flooring once area is cleared.
            Furniture move on completion


                   st
            W/C 1 June - BOH storage space
            Form temporary Site Compound for Skip Storage utilising sections of heras fence panels from previous external works.
            Relocate Fire Alarm Panel and Security Alarm Panels, once all services have been isolated and made safe stripping out s/ceilings
            and partitions can begin. All waste materials will be transferred through BOH and via loading bay and placed into the skip
            storage area. And finally, remove carpet and latex screed and make good.
            Inspect area and once cleared, Install new BOH racking.