ROSENDIN RENEWABLE ENERGY GROUP


                                                                                                                                 “Working between the Bureau of Land Management (BLM),   with the International Brotherhood of Electrical Workers
                                                                                                                                 Riverside County, Indian communities, and CalTrans has   (IBEW) to construct the project. And at its busiest, the jobsite
                                                                                                                                 been challenging,” says Lincoln. “We had to get these highly   has seen 600 workers per day.
                                                                                                                                 regulatory agencies to all agree to the design while
                                                                                                                                 working with them during the pandemic when many         Athos 1 and 2 incorporates 1.48 million First Solar Series
                                                                                                                                 offices were closed.”                                   photovoltaic modules; 18,715 NEXTracker Horizon Single
                                                                                                                                                                                         Axis Trackers; 227,925 foundation piers for the trackers; 7.3
                                                                                                                                 Each of these four entities enforced its own jurisdiction, and   miles of 230-kV transmission line; three substations; and
                                                                                                                                 every work area had to be carefully surveyed and mapped   one shared switchyard.
                                                                                                                                 before construction crews could go in, says Rick Gonzales,
                                                                                                                                 Rosendin division manager at the Athos site.            Gonzales says the overall complexity of the Athos I and II
                                                                                                                                                                                         project led the Rosendin team to embrace the integrated
                                                                                                                                 “One day we would be working on the road in Riverside   project delivery (IPD) method. He says by involving all
                                                                                                                                 County, and the next day we would be dealing with       stakeholders in the permitting process and all facets of
                                                                                                                                 BLM and a different jurisdiction, and then the tribe    subcontracting and supply chain issues, the team has
                                                                                                                                 would come along to see if any (artifacts) were found   established a level of accountability and ownership
                                                                                                                                 on their land,” says Gonzales. “We have easements in    responsibilities required to make this project a “huge success.”
                                                                                                                                 each jurisdiction, but if we step outside the boundaries,
                                                                                                                                 they will fine us, and that makes it very difficult.”   Lincoln says when the team began the project in January
                                                                                                                                                                                         2020, Rosendin would sit around a table with its own in-house
                                                                                                                                 Gonzales says Riverside County required 81 different    engineers, the client, and a couple of key subcontractors and
      SOLAR FARM OVERCOMES                                                                                                       arrays, substations, transmission lines, the operation and   “The IPD process is a little longer upfront, but you get a more
                                                                                                                                                                                         collectively start working on design and going over costs.
                                                                                                                                 permits for the Athos project for things such as photovoltaic
                                                                                                                                 maintenance building, and temporary office trailers.
                                                                                                                                                                                         detailed and thorough set of documents to build off of and
      PERMIT & PANDEMIC HURDLES                                                                                                  “The temporary power permit for the temporary site office   your time frame is shortened significantly,” says Lincoln. “And
                                                                                                                                                                                         with this IPD approach there is very little, if any, change orders
                                                                                                                                 trailer was the most challenging one,” he says. “It took over
                                                                                                                                 six months to get this permit, for a project that is 13 months
                                                                                                                                                                                         because all parties are involved in the design process and
                                                                                                                                 utility connection.”
      By Greg Aragon, Desert Sun                                                                                                 long. We had to run a very large diesel generator until the   costing structure, so it’s been a great tool on the project.”
                                                                                                                                                                                         DESERT DEMOLITION
                                                                                                                                 He says there were multiple reasons why it took the county
                                                                                                                                 so long to issue permits, including a new computer system,   Granite Industrial Inc. was contracted by Rosendin to perform
                                                                                                                                 COVID-19, the retirement of key county employees, and   all site demolition and clearing, site access road construction
                                                                                                                                 changing contractor deliverables. “I’ve been on solar   for 55 miles of access roads, site grading, survey for all post
               massive solar project spanning five square miles is being constructed in the desert near Palm                     projects that require one permit, and 10 or 12 might be a   locations, and installation of the nearly 230,000 foundation
                                                                                                                                 normal amount, but this was the most I’ve seen,” he says.  posts for the trackers.
               Springs, Calif. Once complete, the combined 450-MWac Athos I and Athos II solar installations
      A will cover more than 3,000 acres in Riverside County and generate more than 2,200 GWh per                                Besides dozens of permits, the project also requires a    Tim Burhoe, director of preconstruction for Granite, says
                                                                                                                                 massive amount of infrastructure and labor. Rosendin is   his teams are using a fleet of Vermeer PD10 pile drivers
      year of renewable energy, enough to power 179,000 homes.
                                                                                                                                 utilizing more than 400 employees and union contractors    specifically designed for solar use to install the roughly
                                                                                                                                                                                         12-ft-long piles about 7 ft into the ground. He says two-
                                                                                                                                                                                         person crews work each machine and can install an average
                                                                                                                                                                                         of 5,000 posts per week for Athos I.
      “There is more than 50 miles of roadway going through the   The 200-MW Athos 2 is currently about 98% complete
      property, and the amount of people and resources needed   with an operation date of Dec. 7, and the 250-MW Athos 1                                                                 “This is a challenging process because we have to survey
      to complete this project is pretty massive,” says David   is more than 50% complete with an operation date in                                                                      every point so we can put a giant nail with a ribbon on it that
      Lincoln, senior vice president at Rosendin Renewable Energy   April 2022.                                                                                                          determines which pile goes at each location,” Burhoe says.
      Group. “The ability to bring together 300 to 400 electrical                                                                                                                        Located about 75 miles east of Palm Springs near the small
      tradespeople in the middle of the desert and be on the same   For Athos 1, SB Energy has a power purchase agreement                                                                town of Desert Center, the project site is remote and hot.
      page and motivated to complete the project on time is     to sell the energy created to Direct Energy Business, part                                                               To make it through 120-degree summer days, Gonzales
      really impressive.”                                       of Direct Energy, one of North America’s largest energy                                                                  says crews started work at 5 a.m. and could leave early if
                                                                and energy-related services providers, and a subsidiary
      Rosendin’s Renewable Energy Group (RREG), a division of   of Centrica PLC. For Athos II, SB Energy will sell long-term                                                             they felt ill or too hot. He says the team set up cool-down
      electrical contractor Rosendin, was contracted by subsidiaries   renewable energy credits and output to Chicago-based                                                              stations with ice and shade, arranged water breaks every hour
      of SB Energy US Holdings One Inc. (SB Energy), a renewable   energy provider Exelon Corp.                                                                                          and had safety personnel on site to make sure no one was
      energy corporation and a subsidiary of SoftBank Group Corp.,                                                                                                                       overheating. Rosendin even brought in an ice cream truck
      to design and build the $700-million project. SB Energy says   The project has not been without challenges. The solar farm                                                         to serve the site. 
      the facility is being built to help meet California’s Renewable   is being constructed in the middle of the desert with remote                                                     Source: ENR California
      Portfolio Standard (RPS) to advance renewable energy.     project access and a 3,400-acre jobsite divided between four
                                                                different agencies with myriad permitting requirements.                                                                  Click here to read the full article.