Page 19 - Q4_2021_Corp Newsletter
P. 19

ROSENDIN RENEWABLE ENERGY GROUP


      “Working between the Bureau of Land Management (BLM),    with the International Brotherhood of Electrical Workers
      Riverside County, Indian communities, and CalTrans has   (IBEW) to construct the project. And at its busiest, the jobsite
      been challenging,” says Lincoln. “We had to get these highly   has seen 600 workers per day.
      regulatory agencies to all agree to the design while
      working with them during the pandemic when many          Athos 1 and 2 incorporates 1.48 million First Solar Series
      offices were closed.”                                    photovoltaic modules; 18,715 NEXTracker Horizon Single
                                                               Axis Trackers; 227,925 foundation piers for the trackers; 7.3
      Each of these four entities enforced its own jurisdiction, and   miles of 230-kV transmission line; three substations; and
      every work area had to be carefully surveyed and mapped   one shared switchyard.
      before construction crews could go in, says Rick Gonzales,
      Rosendin division manager at the Athos site.             Gonzales says the overall complexity of the Athos I and II
                                                               project led the Rosendin team to embrace the integrated
      “One day we would be working on the road in Riverside    project delivery (IPD) method. He says by involving all
      County, and the next day we would be dealing with        stakeholders in the permitting process and all facets of
      BLM and a different jurisdiction, and then the tribe     subcontracting and supply chain issues, the team has
      would come along to see if any (artifacts) were found    established a level of accountability and ownership
      on their land,” says Gonzales. “We have easements in     responsibilities required to make this project a “huge success.”
      each jurisdiction, but if we step outside the boundaries,
      they will fine us, and that makes it very difficult.”    Lincoln says when the team began the project in January
                                                               2020, Rosendin would sit around a table with its own in-house
      Gonzales says Riverside County required 81 different     engineers, the client, and a couple of key subcontractors and
 SOLAR FARM OVERCOMES   arrays, substations, transmission lines, the operation and   “The IPD process is a little longer upfront, but you get a more
                                                               collectively start working on design and going over costs.
      permits for the Athos project for things such as photovoltaic
      maintenance building, and temporary office trailers.
                                                               detailed and thorough set of documents to build off of and
 PERMIT & PANDEMIC HURDLES  “The temporary power permit for the temporary site office   your time frame is shortened significantly,” says Lincoln. “And
                                                               with this IPD approach there is very little, if any, change orders
      trailer was the most challenging one,” he says. “It took over
      six months to get this permit, for a project that is 13 months
                                                               because all parties are involved in the design process and
      utility connection.”
 By Greg Aragon, Desert Sun  long. We had to run a very large diesel generator until the   costing structure, so it’s been a great tool on the project.”
                                                               DESERT DEMOLITION
      He says there were multiple reasons why it took the county
      so long to issue permits, including a new computer system,   Granite Industrial Inc. was contracted by Rosendin to perform
      COVID-19, the retirement of key county employees, and    all site demolition and clearing, site access road construction
      changing contractor deliverables. “I’ve been on solar    for 55 miles of access roads, site grading, survey for all post
 massive solar project spanning five square miles is being constructed in the desert near Palm   projects that require one permit, and 10 or 12 might be a   locations, and installation of the nearly 230,000 foundation
      normal amount, but this was the most I’ve seen,” he says.  posts for the trackers.
 Springs, Calif. Once complete, the combined 450-MWac Athos I and Athos II solar installations
 A will cover more than 3,000 acres in Riverside County and generate more than 2,200 GWh per    Besides dozens of permits, the project also requires a    Tim Burhoe, director of preconstruction for Granite, says
      massive amount of infrastructure and labor. Rosendin is   his teams are using a fleet of Vermeer PD10 pile drivers
 year of renewable energy, enough to power 179,000 homes.
      utilizing more than 400 employees and union contractors    specifically designed for solar use to install the roughly
                                                               12-ft-long piles about 7 ft into the ground. He says two-
                                                               person crews work each machine and can install an average
                                                               of 5,000 posts per week for Athos I.
 “There is more than 50 miles of roadway going through the   The 200-MW Athos 2 is currently about 98% complete
 property, and the amount of people and resources needed   with an operation date of Dec. 7, and the 250-MW Athos 1    “This is a challenging process because we have to survey
 to complete this project is pretty massive,” says David   is more than 50% complete with an operation date in    every point so we can put a giant nail with a ribbon on it that
 Lincoln, senior vice president at Rosendin Renewable Energy   April 2022.  determines which pile goes at each location,” Burhoe says.
 Group. “The ability to bring together 300 to 400 electrical   Located about 75 miles east of Palm Springs near the small
 tradespeople in the middle of the desert and be on the same   For Athos 1, SB Energy has a power purchase agreement   town of Desert Center, the project site is remote and hot.
 page and motivated to complete the project on time is    to sell the energy created to Direct Energy Business, part   To make it through 120-degree summer days, Gonzales
 really impressive.”  of Direct Energy, one of North America’s largest energy   says crews started work at 5 a.m. and could leave early if
 and energy-related services providers, and a subsidiary
 Rosendin’s Renewable Energy Group (RREG), a division of   of Centrica PLC. For Athos II, SB Energy will sell long-term   they felt ill or too hot. He says the team set up cool-down
 electrical contractor Rosendin, was contracted by subsidiaries   renewable energy credits and output to Chicago-based   stations with ice and shade, arranged water breaks every hour
 of SB Energy US Holdings One Inc. (SB Energy), a renewable   energy provider Exelon Corp.  and had safety personnel on site to make sure no one was
 energy corporation and a subsidiary of SoftBank Group Corp.,   overheating. Rosendin even brought in an ice cream truck
 to design and build the $700-million project. SB Energy says   The project has not been without challenges. The solar farm   to serve the site. 
 the facility is being built to help meet California’s Renewable   is being constructed in the middle of the desert with remote   Source: ENR California
 Portfolio Standard (RPS) to advance renewable energy.  project access and a 3,400-acre jobsite divided between four
 different agencies with myriad permitting requirements.       Click here to read the full article.


 18  |  THE FEEDER                                                                                  THE FEEDER  |  19
   14   15   16   17   18   19   20   21   22   23   24