Page 16 - REI Corporate Newsletter_Q1 2018
P. 16

The project team is consistently vigilant on             expended (for material and craft man-hours); and the
                                                                                                                                  material and system waste due to oversizing, over        proper sizing of systems in context to the lifespan
                                                                                                                                  specifying, or incorrect design. This is viewed as       and use of the building. We are going to set the
                                                                                                                                  the low-hanging fruit. Some may cynically say that       system sizing for another day and focus on the COW.
                                                                                                                                  contractors optimize solely for their cost benefit,
                                                                                                                                  which is not true. LEAN is one of our most effective     We undertook a new process for fully integrating
                                                                                                                                  ways to combat a lack of construction resources.         constructibility into design on a recent project
                                                                                          LEAN                                    such as UCSF Benioff Children’s Hospital in San          ah-ha moment was our teams use of earliest
                                                                                                                                                                                           at Los Angeles International Airport (LAX). The
                                                                                                                                  Outside of an alternate form of delivery projects,
                                                                                                                                                                                           responsible time where we had the ability to make
                                                                                                                                  Francisco where the design and the construction
                                                                                                                                  team share risk and reward, broaching that design
                                                                                                                                                                                           a durable decision. Clients will often speak about
                                                                                                                                                                                           the last responsible moment for a decision to take
                                                                                                                                  and construction barrier is tough.
                                                                                   AND THE                                        The contracting tradition places the project designers   place. While useful for deliberations or to counter
                                                                                                                                                                                           disorganization, this can lead to compression of
                                                                                                                                                                                           trailing tasks or Un-LEAN default decision making.
                                                                                                                                  and the constructors in opposition. We are missing a
                                                                                                                                  great opportunity to “Ultimate-LEAN” the work (LEAN
                                  DESIGN+BUILD                                                                                    The Designers and Builders are not placed in a           the construction targets are not complete as of yet.
                                                                                                                                  that crosses ancient prejudices and boundaries).
                                                                                                                                                                                           We recently finished the design at LAX, so some of
                                                                                                                                  position to LEAN the cost-of-work (COW) in most
                                                                                                                                                                                           But, by flipping the script and integrating the field at
                                                                                                                                  projects. What is traditionally missed is the overlay
                                                                                                                                                                                           the beginning of design, here’s what happened:
                                                                                                                                  and synchronization of the installation to the design
                                                                    CONSTRUCT                                                     in the design model. If you have been around for            •  Design cost for the work was reduced by 32%.
                                                                                                                                                                                              •  Branch circuit wiring was reduced by 8%.
                                                                                                                                  longer than a cup of coffee on any job, you will hear,
                                                                                                                                  “That’s the contractor’s responsibility,” or, “That’s the
                                                                                                                                                                                              •  Prefabrication increased substantially over
                                                                                                                                  field or engineer’s problem.” What everyone fails
                                                                                                                                                                                                minimum targets (this is still playing out but
                                                                                                                                  to realize is that the overall cost of the project and
                                                                                                                                  the schedule to deliver the project is everyone’s             we have found dozens of other opportunities
                                                                                                                                                                                                that we may not have seen if examined post
                                                                                                                                  problem.                                                      permit).
                                                                         By Bill Mazzetti, Senior VP of Engineering                                                                           •  Design essentially equals the expected
                                                                                                                                  As LEAN processes seek to eliminate waste,                    installation (providing a very sharp cost
                                                                                                                                  Ultimate-LEAN should have the focus of lowering the           estimate from the permit submittal).
                                                                                      LEAN is a lifestyle. It means               total cost of installation and speeding the delivery        •  Coordination between trades and specialty
                                                                                   different things to the various                of the work. To that end, we need to be bold rather           equipment was nearly perfect, eliminating
                                                                                                                                                                                                rework and errors.
                                                                                                                                  than tactical. Most forget that a shorter schedule
                                                                                parties and phases in the design                  offers substantial savings in general condition costs       •  Design schedule for permit submittal was
                                                                               and construction effort. The core                  in the context of similar scopes of work. Assuming            beaten by 10 days.
                                                                                    of LEAN is the elimination of                 that project acceleration will prudently use craft
                                                                              waste and the optimization of the                   labor overtime, we are now faced with providing the      The moral here is do not be afraid to get your builder
                                                                                                                                                                                           involved in the earlier stages with the designers. The
                                                                                                                                  most efficient installation that will lower the COW.
                                                                                work. Pre-Construction (PreCon)                   In reference, craft labor is one of the highest risks    builders are not there to change the design, they are
                                                                                 is the time of the project where                 any project team faces on a project. While fees,         there to make your design as efficient as possible.
                                                                                scope is not completely defined;                  contingency or FFE, might be the sizzle; the steak in    Applying LEAN principals at the PreCon stage allows
                                                                                           we are still conceiving,               a project’s delivery is the COW.                         for preloading of efficiencies into the project that will
                                                                                       designing, and setting the                 There are two basic ways to positively affect            not have to be wrought out during the installation
                                                                                                                                                                                           modeling and construction phase of the work.
                                                                                            job up. That does not                 the COW: coordination and optimization of the
                                                                                                mean that PreCon                  installation resulting in the lowest installed cost
                                                                                             lacks opportunity for
                                                                                                       LEAN gains.




        16    The Feeder | Q1 2018                                                                                                                                                                                      Q1 2018 | The Feeder    17