Grea tfields School

                                                      The Project
                                                      This was a multi-phase project of purpose-built new classrooms
                                                      and support facilities for 1,800 pupils in the 11-18 age group,
                                                      located in Barking, Essex. The construction comprised of the
                                                      latest timber technology to provide a ‘fast track’ approach to a
                                                      new education facility.

                                                      Our Role
                                                      EDP Environmental was commissioned to carry-out the
                                                      detailed MEP Design. We also developed the Energy Strategy
                                                      in accordance with the London Plan and determined the most
                                                      cost-effective way to meet the 30% Carbon offset requirement.
                                                      Our expertise in Thermal Modelling using TAS software was
                                                      valuable in ensuring compliance with BB101 and meeting the
                                                      BREEAM level of “Very Good”.
                                                      Technical/ Factual Statements
                                                       •  A 57kW PV array has been installed on the latest block.
                                                       •  On completion of the scheme there will be over 200kW of
                                                         PV installed throughout the campus.
                                                       •  A fibre optic back bone will be run throughout the various
                                                         buildings to provide a dedicated IT network.  This will also
                                                         be used to carry security, CCTV and access control data
                                                         around the site.


                                                                                                                 OUR projects









                                                      Client            London Borough of Barking
                                                      Architect         Surface To Air
                                                      Main Contractor   MID Group
                                                      Services Contractor  Greenside Integrated Services
                                                      Project Value     £ 35M