KAEDAH BUANG & GANTI ( Dengan/Tanpa Geotekstil)




          Determination of Depth Removal
          Klausa 20.2.2 ( JKR Road Specification :

          Section 20) & Klausa 2.2 ( JKR Building
          Specification : Section V)



           The depth of removal shall be as shown
           in the Drawing or as determined by trial
           pits or JKR/Mackintosh Probe test as
           approved by the S.O. The trial pits or
           probe test shall be carried out at
           locations as indicated in the Drawing or
           as instructed by the S.O. The apparatus
           used shall be the standard JKR probe or
           Mackintosh probe. Procedure of works
           and details of the JKR probe and
           Mackintosh probe are as per latest
           revision of JKR Standard Specification for
           Roadworks, Section 17: Site
           Investigation.