Page 19 - PENGAWASAN KERJA RAWATAN TANAH
P. 19
KAEDAH BUANG & GANTI ( Dengan/Tanpa Geotekstil)
CORRECT METHOD FOR EXCAVATION
Excavation Depth = D
EGL
Backfill for construction
D access or working
platform
**The required excavation depth shall not be measured from
backfill for construction access or working platform
EGL
Backfill for construction
D access or working
platform
**The required excavation depth shall be measured from ORIGINAL
GROUND LEVEL (OGL).