Page 42 - PENGAWASAN KERJA RAWATAN TANAH
P. 42

TIANG BATUAN (STONE COLUMN)                                                   SPESIFIKASI PIAWAI BANGUNAN JKR : SEKSYEN V – KLAUSA 6
                                                                                    SPESIFIKASI PIAWAI JALAN JKR : SEKSYEN 20 – KLAUSA 20.6



            Sebelum pembinaan : Cl 6.3 & Cl 20.6.3

            1.      Kontraktor perlu mengemukakan Method Statement kaedah Pembinaan 2 minggu
                    sebelum pembinaan untuk kelulusan SO yang mengandungi:-

            a)      A detail construction sequence.

            b)      Shop drawing

            c)      Design calculation of key temporary works endorsed by PE

            d)      Material, plants & labor requirement at each construction stages
            e)      Rate of production output bases on resources allocated.

            f)      EMP

            g)      Other infomationa relevant to the works.