Page 42 - PENGAWASAN KERJA RAWATAN TANAH
P. 42
TIANG BATUAN (STONE COLUMN) SPESIFIKASI PIAWAI BANGUNAN JKR : SEKSYEN V – KLAUSA 6
SPESIFIKASI PIAWAI JALAN JKR : SEKSYEN 20 – KLAUSA 20.6
Sebelum pembinaan : Cl 6.3 & Cl 20.6.3
1. Kontraktor perlu mengemukakan Method Statement kaedah Pembinaan 2 minggu
sebelum pembinaan untuk kelulusan SO yang mengandungi:-
a) A detail construction sequence.
b) Shop drawing
c) Design calculation of key temporary works endorsed by PE
d) Material, plants & labor requirement at each construction stages
e) Rate of production output bases on resources allocated.
f) EMP
g) Other infomationa relevant to the works.