                             THE TURNING POINT – COLLECTIVE RESOLVE


                         ------------------------------------------


                     STRATEGIC INTERVENTIONS


                     Joint Visit by IG NEZ & IG Jorhat: A pivotal moment where 3
                     additional barracks were allotted for troops and offices.

                     Phased Upgradation: Specialized workshops, BWS, and were

                     prioritized



                     27 June 2024         Temporary shed was created for placement of DG
                                          sets to resolve the power outage issues in the main
                                          office.    The  GCO  ordered  to  dismantle  above  set
                                          through Virendra Rajput AC building. Above act was
                                          very  unfortunate  and  very  disheartening.  So  the
                                          matter has been taken to ADG OPS DTE to resolve
                                          current impasse.
                     Rising from Challenges


                     The  relentless  efforts  of  Commandant  7  Signal  Bn  and  his  team
                     transformed  hurdles  into  milestones.  Temporary  structures  were
                     repurposed,  and  collaborations  with  engineering  wings  accelerated
                     progress.

                                          On hearing of this matter, ADG OPS DTE has
                     July 2024            formed high level commit consisting IG ZONE NE
                                          ZIG OPS JORHAT DIG SIGNAL RANGE. After
                                          the discoursing the issue at length. Above commit
                                          found insufficient infrastructure have been provided
                                          by GC which required to re-evaluate. Later above
                                          commit vide minutes of meeting on infrastructure
                                          for 7 signal Bn allotted three barracks 180 men

                                          barrack(namdapha), and two 120 men barracks
                                          (majule and kaziranga).

                     13 July 2024         Opening  of  Hathi  Chowk  canteen.  It  is  biggest
                                          milestone achieved by integration of wet canteen in 7