Page 140 - CompleteBooklet2021
P. 140
3. Track machine utilisation:
Progress up to
Sl No Type of Machine Target 2021-22
Sept ‟21
1 Tie Tamping Machine 1400 Km 795.650 Km
2 Unimat 600 Pts 266 Pts
4. Level crossing works
2020-21 2021-22
Sl
No Description of item Boards Internal Progress Boards Internal Progress
Target Target Target Target (22.10.21)
Construction of Road Over
1 - - - - - -
Bridge
Construction of Limited
2 10 12 14 09 21 03
Height Subways
Closure of Level crossings on
3 - - - - - -
account of diversion of Traffic
Closure of Level crossings on
4 - - - - - -
account of meager traffic
5. Relaxation of Permanent Speed Restrictions.
Target 2021-22 = 02 Nos
Completed = 03 Nos
Sl
No Section Bet Stns Km /TP SR Reason for SR Remarks
Entering into single
1 SC-DHNE FM Yd 15/0-100 30 Kmph Deleted
linen from Double line
Pt No: 13B laid in Deleted on DN
2 SC-DHNE BDVL Yd 20/900-21/0 60 Kmph
transition line and relaxed
Pt No: 7B laid in to 100 Kmph on
3 SC-DHNE UR Yd 27/300-200 60 Kmph
transition UP line.
6. RAIL / WELD FAILURES
Year wise comparison
Year RAIL WELD
2019-20 1 16
2020-21 0 11
2021-22 (Sept‟21) 0 3
136