Page 141 - CompleteBooklet2021
P. 141
MONTH WISE ANALYSIS OF RAIL / WELD FAILURES
2019-20 2020-21 2021-22
Weld Weld Weld
Month Rail Month Rail Month Rail
FBW SKV TOT FBW SKV TOT FBW SKV TOT
Apr-19 0 0 1 1 Apr-20 0 0 0 0 Apr-21 0 0 0 0
May-19 0 0 0 0 May-20 0 0 0 0 May-21 0 0 0 0
Jun-19 1 0 2 2 Jun-20 0 0 0 0 Jun-21 0 0 1 1
Jul-19 0 0 2 2 Jul-20 0 0 0 0 Jul-21 0 0 1 1
Aug-19 0 0 2 2 Aug-20 0 0 0 0 Aug-21 0 0 0 0
Sep-19 0 0 3 3 Sep-20 0 0 1 1 Sept-21 0 0 1 1
Oct-19 0 0 1 1 Oct-20 0 0 0 0
Nov-19 0 0 0 0 Nov-20 0 2 1 3
Dec-19 0 1 3 4 Dec-20 0 1 2 3
Jan-20 0 0 0 0 Jan-21 0 0 0 0
Feb-20 0 1 0 1 Feb-21 0 1 2 3
Mar-20 0 0 0 0 Mar-21 0 1 0 1
1 2 14 16 0 5 6 11 0 0 3 3
7. Progress of other mission items
Progress
Sl No Work Target 2021-22
(Sept‟21)
1 USFD testing 2475 Km 1293 Km
2 Painting of Rails 10 Km 29.4 Km
3 Painting of weld collar 2000 Nos 1300 Nos
4 Reconditioning of points & crossings 80 Pts 45 Pts
5 Scarp offered 1090 MT 350 MT
9. Maintenance of service and residential buildings:
The following works were carried out during the year 2019-20 for
maintenance of staff quarters.
Target Progress
Sl No Work
2021-22 (Sept‟21)
1 Directed maintenance of Buildings 90 47
2 Repairs to leaky roofs of Quarters 50 26
3 Provision of Pathways 50 26
4 Replacement of Doors & windows in Quarters 100 51
5 Provision of Mosquito Mesh in Quarters 120 56
137