  PLANNING

            SANCTIONED WORKS

            PRELIMINARY WORKS PROGRAMME (PWP) UNDER TRAFFIC FACILITIES
            (PH: 1600)
                                                                                           (Rs. in 000‟)
          Sl.                                    Year of     Anticipate
          No        Description of work         Sanction       d Cost                       Status
           1.   Provision of New crossing        2010-11         Cap       Works in progress.
                station at Pedashapur                         16,95,00
                between
                Umdanagar&Timmapur  on
                SC-MBNR section.
           2.   Provision of 04 new              2017-18      38,26,00     1. Work in Progress for Bridge &
                crossing stations.                                            Earth Work. Land Acquisition for
                                                                              Station Building under Process by
                1. Wanaparthy-Kaukuntla
                  (18.27 kms)                                                 State Govt.  of Telangana  (3
                                                                              Stations) & Andhra Pradesh (01

                2. Monopad-Alampur                                            Station).

                     (16.10 kms)                                           2. Exemption received for 01 Station

                3. Itikiyala-    Monopad                                      (Perur) between WPR-KQQ. At
                                                                              present only  one station is planned
                   (13.58 kms)                                                between WPR-KQQ (Perur station)
                                                                              and remaining 03 stations will be
                4. Ulindakonda-     Veldurthi                                 taken along with doubling.
                   (12.06 kms)
                                                                              TDC- 31.03.2021
           3.   Nizamabad:  Remodelling          2018-19       8,79,84     CRS  sanction  obtained,  Agencies
                of yard arrangements  for                                  Available,  Work  not  started  due  to
                providing additional                                       involvement  of shifting of Goods shed
                platforms and one full                                     to  JKM  station.  Proposal  for  shifting
                length  dead end spur.                                     of  Goods  Shed  to  JKM  and
                                                                           development       of    goods      shed
                                                                           circulating area at JKM is pending for
                                                                           sanction  at  Railway  Board.  TDC
                                                                           30/03/2023
           4.   Jankampet Jn: Additional         2019-20      11,30,00     The work was proposed under  PWP
                two loop lines.                                            2019-20 and approved by GM under
           5.   Falaknuma:  Standard double  2019-20           8,57,00     Umbrella works.
                line layout  by provision of                               Railway board accorded sanction on
                DN loop line (standard                                     29.09.2021.
                double line layout)                                        Necessary ESPs to be prepared.
           6.   Talamadla:  Additional loop      2019-20       6,37,00     The work was proposed under  PWP
                line (standard layout).                                    2019-20 and approved by GM under
           7.   Sirnapalli: Additional loop      2019-20       6,37,00     Umbrella works and sent to Railway
                line (standard layout).                                    board for approval.