7.  Approach  Warning  System  for  both  Up  and  Dn  directions  in  02  mid-section
                   interlocked LC gates provided at LC189A & LC12. All 39 mid-sections interlocked LC
                   gates have been completed.

















               8.  Carried  out  signaling  alterations  in  relay  room  and  replaced  operating  panel  in
                   connection  with    proposed  Satellite  Track  Machine  Depot  at  Cavalry  barracks  and
                   commissioned.
















               9.  Carried out linking of datalogger with Control office application (COA) for reporting
                   train arrival/departure  timings at Mahbubnagar,  Medchal & Umdanagar stations.
















               10. Existing  single  line  pushbutton  token  less  block  instrument  between  BVO-DHNE
                   section replaced with UFSBI along with  HASSDAC of CEL make working on dual
                   media (OFC & Quad cable).