     There are a number of challenges in providing water to the site. Costs included are an estimation based on a 5,000
     litre tank, a pump, trenching and reinstatement. This solution and cost are an estimation only and advice from a
     professional plumber should be sought.  If funding is available for phase one in its entirety, we recommend the use
     of a project manager and have included a budget of $24,000 for this.
     Stage 1 Trail Hub and Pump Track Pricing
                                                                          TOTAL                              $212,670.00
                                                                          Inflation Totals      Year 1
                                                                                                $219,263
     *Carpark (Optional Extra)
                                                                            Total                               $110,000
                                                                            Inflation Totals      Year 1
                                                                                                  $113,410