Page 18 - Gi_March2020
P. 18

going live


                   A 12-week schedule of works was   operative manoeuvres the arms around   on the Wickwar Road project alone.
                 drawn up to ensure that the onsite   the pipe and then applies sufficient   Open cut would have taken 40
                 team worked towards the scheduled   pressure to crack the pipe. The MACAW   weeks to complete, but LMI took just
                 completion deadline. This schedule   may be used on cast iron pipes inserted   11. The delivery team also calculated
                 involved a one-way-fed live insert with   with PE, if required.   that disruption to local residents
                 an estimated ten insertions over 4.2km   Quick to set up, easy to operate,   and road users was reduced by 100
                 – an average of 350 metres a week.  highly manoeuvrable and safer and   minutes per week.
                   The most ambitious insertion was a   faster than a ‘podger bar’ or sledge   Mr Breakey said: “The use of
                 record breaking 1,014 metres in one   hammer, the MACAW Cracker is ideal   innovation on standard jobs can be a
                 continuous length, taking just under   for use with LMI projects and offered a   win-win for the customer, our contract
                 three hours using the SVI Large Pipe   number of benefits to the project team.   partners, and us. Wickwar Road
                 Handler, which is suitable for PE   These included:               demonstrates how it pays to innovate,
                 diameters of 250mm to 1,200mm.      No required access around the entire   facilitating a safer, quicker, and less
                 The complete laying of the pipe and   pipe circumference          disruptive scheme while delivering
                 abandonment for this section was     Controlled pressure applied – suitable   value for money.”
                 achieved in two weeks. Until that point,   on abandoned and inserted mains,   The project was completed a week
                 the biggest previous insertion achieved   without damaging internal PE  ahead of schedule on 14 December 2018.
                 by the project team in a single push was     Various power source options to   Onsite support and consumables were
                 630 metres.                       accommodate site conditions     provided by Steve Vick International.
                   The major benefits provided by LMI                                The work undertaken forms part
                 meant the technique was the obvious                               of Wales & West Utilities’ 30-year
                 choice for MUS.                  Innovation played a major        programme to deliver essential gas mains
                   Innovation played a major role in   role in the project’s success.   replacement and associated works across
                 the project’s success. In total, nine   In total, nine innovative tools   Wales and the South West of England.
                 innovative tools were used during                                   The programme involves the
                 the project, saving time, money and   were used during the project,   feasibility, design, programme
                 effort over conventional practices and   saving time, money and effort   management and delivery of 3,500km of
                 improving safety and disruption.   over conventional practices and   metallic gas mains replacement (420km
                   A good example of the type of   improving safety and disruption  per year) with approximately 40,000
                 innovative tool used to deliver the                               customer gas connections each year.
                 project is the SVI MACAW pipe                                       The geography incorporates both
                 crackers, so-called due to the pipe   Other innovative tools used over   densely populated areas of Cardiff,
                 cracking arms’ resemblance to the beak   the course of the works included the   Newport and Bristol, areas of special
                 of the South American bird.      SVI Large Diameter Pipe Handler, soil   interest such as Bath as well as sparsely
                   Breaking out cast iron mains has been   picks, ProFuse peelable pipe, System   populated areas of the Welsh Valleys,
                 a longstanding health and safety concern   1 Twin Bagtube, crawler cameras, PE   Somerset, Devon and Cornwall.
                 in the gas industry, largely due to the   flowstopping, as-laid drawing capture,    The record-breaking ‘live’ live mains
                 labour-intensive tooling available.  and reusable Supatees.       insertion at Wickwar was shortlisted
                   The MACAW attaches to the quick-  It is estimated that the adoption   for Project of the Year at last year’s
                 hitch or bucket pins of a mini excavator.   of the LMI process, rather than the   IGEM & EUA Gas Industry Awards.
                 Controlled from the cab, and using   traditional open cut method, led to total   To nominate for the 2020 awards,
                 the excavator’s hydraulic power, the   cost savings of approximately £500,000   go to bit.ly/GasAwards20




































          18



                                                                                                                  13/02/2020   13:32
        MUSLiveMains.indd   3
        MUSLiveMains.indd   3                                                                                     13/02/2020   13:32
   13   14   15   16   17   18   19   20   21   22   23