Page 37 - Gi flipbook September 2018
P. 37

I requested that a feasibility study be
                 undertaken. Included in this was: a   FIGURE 1 View from the centre of the river, on the left is the steep banks of the TLHB
                 GPS topographical survey,        where the major erosion is occurring and also where there is a whirlpooling effect
                 environmental studies on both sides
                 of the river and some high level
                 design ideas for best value protection
                 of the pipeline. Through evaluation of
                 this study and other projects of this
                 nature, it was decided that the most
                 viable course of action would be a full
                 river bank remediation/river diversion.
                   The current state of the river bank
                 is shown in Figure 3, where it is
                 evident the river is eroding a huge
                 hole in the TLHB (true left hand bank)
                 and it is only getting worse.
                   The pipeline in jeopardy is known as
                 a T/SP/P/18 pipeline, meaning that the
                 weld records are not available
                 anymore. Due to this fact, emergency
                 procedures would be applied if the
                 pipeline were to be exposed; line
                 pressure would likely be reduced by
                 15 per cent as a precaution and the
                 welds would need to be excavated
                 and checked by specialists, who would
                 make a decision on their quality
                 against pipeline specification T/SP/P/11.
                   If these did not meet the industry   FIGURE 2 Aerial view of the River Mersey project, showing the direction of the water flow
                 standard, remedial action would be   (top right to bottom left), The Waterside Hotel, National Grid pylons, Cadent HP pipeline,
                 necessary. This would usually take the   Network Rail and M60 Motorway
                 form of an epoxy shell applied to the
                 weld to strengthen it. This procedure
                 is costly, so should be avoided if
                 possible. If the pipeline were to be
                 undermined, the total cost of the
                 procedure and shelling would be in
                 the region of £350k. Additionally,
                 action would still be required to
                 address the issue of the river with a
                 project like this one.
                   It is obvious that the erosion spot
                 around the middle of the drawings is
                 a huge issue. To add to this, there is a
                 section of concentrated invasive plant
                 species – Japanese Knotweed, Giant
                 Hogweed and Himalayan Balsam
                 – these will need to be dealt with
                 during the works.
                   The grey shape in the water channel
                 is composed of river silts and sands
                 deposited due to the drop in energy
                 on an inside bend of the river. This is
                 the start of another migration of the   restriction for any machinery.  THE SOLUTION
                 river; the small channel between the   The Waterside Hotel, which sits on   Excavation of the old channel to
                 TRHB (true right hand bank) and the   the light grey area of the inside bend,   divert the majority of the flow of
                 silt bar will eventually close and force   owns the land through which we will   water will allow for a safe work area
                 all the water to be pushed further   require access. The access road to the   to commence remediation of the
                 outwards. This is a completely natural   car park is also in danger of erosion   TLHB. Works can then start on the
                 process, but will only make the   and collapse, so an agreement has   TRHB, where we will undertake this
                 erosion near the pipeline worse.   been made with the owners regarding   excavation of the old channel. We will
                 Another challenge is that National   further separate works. On the other   build up a small section at the top and
                 Grid have 400kV overhead cables   side of the river there is a farmer who   bottom of the channel to act as a
                 that run directly above the main   uses this field mainly for grass, but   dam. When the TRHB has been
                 works area creating a height     sometimes for cattle.            constructed with rock armouring and



                                                                                                               37


        IGEMNews_YPPC.indd   2                                                                                    16/08/2018   13:19
   32   33   34   35   36   37   38   39   40   41   42