ASSET FAILURES 27.15 35.6 32.75 39.5 36.3 24.48
PUNCTUALITY LOSS 15 2.7 12 6.97 9 7.14
ASSISTANCE REQUIRED:
A proposal for creation of 3posts of (CMS-2 & CMA-1) for increased
administrative approval.
The proposal forwarded to PCPO/SC Vide Lr. No. SCR/P-
SC/Authr/1651/COP/ELS/KZJ Dt: 12.07.2019. It was returned with
observations from FA&CAO office. With remarks, reply was sent to
HQRS. The proposal is pending at Head Quarters.
A proposal for creation of 117 posts for increased assets, after initial
forwarded to PCPO/SC Vide Lr. No. SCR/P-SC/Authr/165/COP/ELS/KZJ
VI/302 Dt:
03.03.2020 has initially concurred for 20 Posts and the proposal is
pending at head quarters.
For creation of 12 new non-gazette posts, PCEE/SCR accorded
approval duly surrendering 17 Tech-III posts of DLS/KZJ. But, So far, it has
not been materialized. It is requested to provide matching surrender
from DLS/KZJ or from HQRS vacancy bank.