Page 95 - Annual Report 2018
P. 95

INFRASTRUCTURE |                                         FY 2018 GAA BUDGET UTILIZATION RATE





              INFRASTRUCTURE PROJECTS

                                                                                                         Date             Expected Date of
                                       Name of Project                            Allocated Budget                                                Status
                                                                                                        Started             Completion
              Construction of Food Technology Laboratory Building              4,667,590.92       01/08/2017         24/01/2018              Completed
              Improvement of Socio-Cultural Office                             723,554.78         16/07/2018         15/09/2018               Completed
              Improvement of the Sport's Office                                732,537.94         16/07/2018         15/09/2018               Completed

              Enhancement of Food Innovation Center                            260,900.00         20/07/2018         03/08/2018               Completed
              Construction of Mushroom Laboratory Phase I                      323,771.57         23/07/2018         12/09/2018              Completed
              Construction of Three-Storey Library Building                    19,124,449.11      02/08/2018         01/02/2019              On going

              Renovation of RM CCIT Building                                   4,422,596.04       01/09/2018         30/10/2018              On-going
              Construction of Generator Housing                                217,560.09         01/09/2018         30/09/2018              Completed
              Renovation of Old Stage                                          249,018.83         17/09/2018         16/11/2018              Completed

              Construction of Streetlight Along Campus Premises                435,000.00         15/10/2018         15/11/2018              Completed
              Construction of Two Commercial Stalls                            834,446.96         15/10/2018         14/01/2018              On-going

              Construction of Goat Housing                                     249,900.00         03/12/2018         02/01/2018              On-going
    81        Construction of Mushroom Laboratory Phase II                     184,108.96         17/12/2018         26/01/2018              On-going

              REPAIR OF TBI BUILDING                                           1,976,587.50       Sep 26, 2018       Jan 23, 2019            On-going

              General Education Building Phase 1                               2,006,520.90       Feb 14, 2018       May 15, 2018            Completed
              (17% Remaining Works)

              Renovation of CBAPA Building                                     2,458,161.53       Aug 1, 2017        Dec. 31, 2017           On-going
              Renovation of CBAPA Building                                     2,458,161.53       Aug 1, 2017        Dec 29, 2017            Completed
              Renovation of University Library                                 2,881,958.43       May 2, 2018        Sep 29, 2018            On-going

              Rehabilitation of Semen Processing Laboratory                    3,203,125.13       Feb 2, 2018        Jul 16, 2018            On-going
              Construction of Cacao Processing Center                          3,249,805.11       Oct 17, 2018       Feb 13, 2019            On-going
              Repair of Freshwater Fisheries Center                            3,369,199.00       Oct 18, 2018       Feb 14, 2019            On-going

              Rehabilitation of Amphitheater                                   3,620,802.75       Apr 11, 2018       Sep 8, 2018             On-going
              Concreting of Road Network from Infirmary to                     5,203,680.26       Dec 6, 2017        May 29, 2018            On-going
              Amphitheater
     ISU ANNUAL REPORT 2018