Page 4 - Presentation
P. 4
1. Devegetation
2. Scrap / useable material removal
3. Debris / insulation / Excess earth
4. Collection & Disposal of Item Nos 1, 2 & 3 and others
5. Zone Contract (House Keeping)
6. Zone Contract (Mechanical )
7. Comprehensive Electrical Contract
(Complete off site area)
8. Comprehensive Instrumentation Contract
(Complete off site area)
9. Asphalt Tank Farm
10. Complete recovery of Asphalt & Oil in Reclamation
units
11. Pipeline corridor:
12. Prevention of Oil spillage in the dyke & Dyke canals
13. Concreting on road sides / dyke and dyke wall
14. Concrete ramp at dyke walls (Crude Tanks)
15. Trimming of Asphalt pad around the tank
16. Painting of Storage Tanks
17. Special painting at wind girder area