Page 18 - WaikaiaForestTrailsSummary
P. 18

03.



      NOTE: Investment in the mature stand at the entrance to the trail network should be limited to what is necessary. This
      area is due to be felled in 2026-2028. There will be some machine work, but this area is expected to be relatively easy
      to build in and an ideal opportunity for professionally supported volunteer work.




                                                                                 TOTAL                          $178,612
                                                                                 Inflation Totals  Year 2                         $189,858






      Green Loop












                                                                                          FR



                                                                     FSR

                                                                              FR































      Forest Road Climb




     The proposed green loop is an opportunity to provide visitors with a longer ride by utilising forest access roads and
     opening up the wider hill, without the investment of purpose-built trails. We consider this limited in its appeal, but
     will add value with little additional cost. This linking forest roads will need to be proofed once access to the site is
     granted. We expect the majority of riders will loop the fun green and blue descents.



                                                                 18
   13   14   15   16   17   18   19   20   21   22   23