Page 14 - WaikaiaForestTrailsSummary
P. 14

03.









































     There are a number of challenges in providing water to the site. Costs included are an estimation based on a 5,000
     litre tank, a pump, trenching and reinstatement. This solution and cost are an estimation only and advice from a
     professional plumber should be sought.  If funding is available for phase one in its entirety, we recommend the use
     of a project manager and have included a budget of $24,000 for this.




     Stage 1 Trail Hub and Pump Track Pricing

                                                                           TOTAL                              $212,670.00
                                                                           Inflation Totals       Year 1                              $219,263







     *Carpark (Optional Extra)

                                                                           Total                                $110,000
                                                                           Inflation Totals      Year 1                               $113,410