MOCKDRILLS





      MOCK DRILL AT FGD MOUDA PROJECT


       Emergency for which mock-drill is conduct: Electrical Shock
       Type of mock-drill: Practice Drill
        Overall response time: 10 mnts

          Sr. No.              Good points of mock drill                     Observed shortfall in mock drill

                      Observer had seen in time and called to safety       Lack of emergency contact number with
             01
                                       personnel.                                       the workers
             02           Ambulance reached in time at location.



                      Corrective actions initiated related to observed
          Sr. No.                                                         Responsibility            Target
                        shortfall in mock drill, Area of improvement

                    Will aware the workers and staff through TBT          Santhosh Kumar
             01                                                                              Immediately after drill
                    about emergency contact number                      (ACIL Safety officer)
                    Ambulance number shared to all the workers           Santhosh Kumar
             02                                                                              Immediately after drill
                    through TBT.                                       (ACIL Safety officer)