REQUESTED EXTENSION 21
Due to the eight-month delay of the finalisation of the MoU between the CUT (Lead
University) and UEL (UK partner University), the UEL has not been able to progress in
the project. For this reason, it is requested that the duration of the project is extended
by eight months so that the project can be completed by 1 December 2023.
A proposed new work plan has been attached for the extension of the project. CCWP1
and WP2 have both been adjusted by eight months for the UEL (UK Partner University).
CCWP2, WP1 and WP3 have seen minor adjustments or extensions to fit the new
extension. The dates for meetings have also been rescheduled to suit the adjusted
dates.
Due to the eight-month delay of the finalisation of the MoU between the CUT (Lead
University) and UEL (UK partner University), the UEL has not been able to progress in
the project. For this reason, it is requested that the duration of the project is extended
by eight months so that the project can be completed by 1 December 2023.
A proposed new work plan has been attached for the extension of the project. CCWP1
and WP2 have both been adjusted by eight months for the UEL (UK Partner University).
CCWP2, WP1 and WP3 have seen minor adjustments or extensions to fit the new
extension. The dates for meetings have also been rescheduled to suit the adjusted
dates.