Page 95 - Performance / Statistics
P. 95
NEW WORKS PROPOSED UNDER PWP 2020-21:
(Rs. in 000‟)
Sl.
No Description of work Cost Status
1. Kacheguda: Extension of shunting 34,19,58 Proposal has been shortlisted by
neck from existing 526 mts to 730 Hqrs and sent to Railway board.
mts duly constructing bridge on
Moosi River.
2. Dupadu: Provision of Standard 9,70,00 Proposal has been shortlisted by
layout station. Hqrs and sent to Railway board.
3. Bolsa: Provision of Standard layout 11,51,28 Proposal has been shortlisted by
station. Hqrs and sent to Railway board.
4. Bye-pass line between 138,55,87 Proposal has been turned down by
Sitaphalmandi-Malkajgiri. Hqrs.
SANCTIONED WORKS
LUMPSUM WORKS PROGRAMME (LSWP)
(Rs. in 000‟)
Year of Latest
Sl. Description of work Sanction Anticipate Remarks /Present status
No d Cost
1. Kacheguda : 2014-15 99,42 Work in progress, track linking completed.
Provision of additional Line will be connected along with KCG
Stabling line Yard Modification for IOH Shed. SIP
approved for shifting (Revision) of shunt
permit indicators for IOH shed work at
KCG and it involves shifting of OHE
portal. TDC-31.07.2021
2. Sivungaon: 2019-20 25,53 Work in progress. Bill to the Tune of 17.05
Provision of Shunt Lakhs pending. TDC-31.05.2021
signals.
DOUBLING Works:
(Rs. in 000‟)
Outlay
Latest
Sl. Description of Year of Anticipate propose Remarks /Present status
No work Sanction d for
d Cost
2019-20
1. Secunderabad – 2015- 10,00,00 200,00,0 1. Detailed estimate sanctioned by
Mahbunnagar 16 (CAP) 0 (EBR Railway board for an amount of
(110 kms) 728,10,0 IF) Rs.728.10 crs on 18.11.2015.
0 2. ESPs of all stations between UR-
Doubling with EBR (IF) MBNR approved from operating
Electrification point of view by Division and Hqrs.
3. Doubling works between SHNR-
GLY (28.76 kms) completed and
commissioned on 15.09.2020.
192