Page 96 - Performance / Statistics
P. 96
MMTS Phase-II works:
Sl. Name of the work Status
No
1 MMTS (Phase-II): Doubling between BMO-MED was commissioned
MED – MLY, on 02.04.2019.
STPD „B‟ – STPD „A‟ cabin Doubling of track between STPD „A‟ and STPD „B‟
(chord line) and chord line yet to be finalized.
FM - UR – GMR Airport. FM-UR section works in progress and targeted for
commissioning during Feb‟20.
RE works:
Sl. Description of Year of
No PB No. work Sanction Remarks /Present status
1 2019-20 Doubling with 2015-16 Doubling works with RE between was
Electrification of sanctioned vide Pink Book, Page
MMR-MUE- No.7.2.4, Item No.44 in the year 2019-
DHNE section 20.
Works have been sanctioned but to be
carried out.
New lines:
1) Akkanapet – Medak (17.20 Kms):
Work sanctioned vide PB 2012-13.
The ESPs of Akkanapet and Medakwere approved and works is in
progress. All Tenders for 17.20 Km has been finalized and targeted for
commissioning during 2020-21.
NI work done from 14.05.2019 to 18.05.2019 (3 days PRE NI and 02 days
NI) at Akkanapet and additional loop line was commissioned on
18.05.2019.
2) Manoharabad – Kottapalli (148.90 kms):
Work sanctioned vide PB 2006-07.
MANOHOHARABAD - GAJWEL (30.10 KMs) COMMISSIIONED ON
19.06.2020 UNDER 'ONE TRAIN ONLY SYSTEM'.
3) Mahbubnagar – Munirabad (222 kms):
Work sanctioned vide PB 1997-98.
Phase-I works: Devarkadra to Krishna Works between Devarkadra to
Jakliar section completed and one train only system introduced on
25.03.2017.
CRS Authorization for new line extension between Jaklair to Makthal
commissioned on 05.06.2020 under „ONE TRAIN ONLY SYSTEM‟.
The works between Makthal to Krishna is in progress.
193