Quantity Surveying: Guideline for Quantity Surveyor                                                         Chapter 6



                   15.    After the selection process to select the contractor, Quantity Surveyor must be
                          provide  a  letter  of  acceptance  to  qualified  contractor  within  the  tender  validity
                          period.

                             i.   Interpret the contents of letter acceptance.
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________
                                 _________________________________________________________________

                            ii.   Explain  clearly  the  steps  of  providing  letter  of  acceptance  to  qualified

                                 contractor for a government practice.