DM.19.1025 Wealden House, Lewes Road, Ashurst Wood, West Sussex. RH19 3TB

               Proposed new build residential development consisting of 54 units following the
               demolition of all existing site buildings.



               Due to the proximity of adjacent residential premises, should the application be approved,
               the following conditions aimed at minimising disturbance to residential amenity during
               demolition and construction are recommended. In addition, the proximity of this site to a
               busy A road suggests that existing background noise levels are likely to be fairly high due to
               traffic. A condition is therefore recommended to protect the amenity of future residents:


               Construction hours: Works of demolition or construction, including the use of plant and
               machinery, necessary for implementation of this consent shall be limited to the following
               times:


               Monday to Friday      08:00 - 18:00 Hours
               Saturday              09:00 - 13:00 Hours
               Sundays and Bank/Public Holidays no work permitted.


               Reason: to protect the amenity of local residents.



               Deliveries: Deliveries or collection of plant, equipment or materials for use during the
               demolition/construction phase shall be limited to the following times:


               Monday to Friday:  08:00 - 18:00 hrs;
               Saturday:               09:00 - 13:00 hrs
               Sunday & Public/Bank holidays: None permitted

               Reason: to protect the amenity of local residents.




               Control of Demolition/Construction noise: Demolition/Construction work shall not
               commence until a scheme for the protection of neighbouring properties from noise generated
               during demolition/construction work has first been submitted to, and approved in writing by,
               the Local Planning Authority. The scheme shall be in accordance with BS5228-1:2009
               ‘Noise and Vibration control on construction and open sites’. The scheme as approved shall
               be operated at all times during the demolition/construction phases of the development.

               Reason: To protect neighbouring residents and residences from noise and vibration.