Page 216 - National Electrical Price Guide
P. 216
10-29-18
100-2
SITE WORK - Re-Bar
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
#3 0.32 0.75 0.01 0.01 0.01 0.02
#4 0.40 0.90 0.01 0.01 0.01 0.02
#5 0.56 1.25 0.01 0.01 0.01 0.02
#6 0.72 1.65 0.02 0.03 0.03 0.03
#7 0.88 2.00 0.02 0.03 0.03 0.03
#10 1.52 3.45 0.02 0.03 0.03 0.03
SITE WORK - Chasing Concrete
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale LOW MED HIGH X-HIGH
6" x 12" 8.15 16.30 0.40 0.50 0.60 0.70
6" x 18" 9.75 19.50 0.60 0.75 0.90 1.05
SITE WORK - Hole Digging
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
12" x 24" 0.00 0.00 1.00 1.25 1.50 1.75
18" x 36" 0.00 0.00 1.50 1.88 2.25 2.63
18" x 48" 0.00 0.00 2.00 2.50 3.00 3.50
18" x 60" 0.00 0.00 2.75 3.44 4.13 4.81
24" x 48" 0.00 0.00 2.50 3.13 3.75 4.38
24" x 60" 0.00 0.00 3.00 3.75 4.50 5.25
24" x 72" 0.00 0.00 3.50 4.38 5.25 6.13
SITE WORK - Miscellaneous
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Tie Wire 0.04 0.10 0.01 0.01 0.01 0.02
Color Concrete 9.90 17.85 0.00 0.00 0.00 0.00
Cubic Yard of Sand 15.00 27.00 1.00 1.25 1.50 1.75
Cubic Yard of Gravel 30.00 54.00 0.50 0.63 0.75 0.88
Auger Base Hole 75.00 135.00 1.00 1.25 1.50 1.75
Marker Tape 0.09 0.30 0.01 0.01 0.01 0.02
Hand Tamper 0.00 0.00 0.20 0.25 0.30 0.35
Machine Tamper 0.65 1.20 0.08 0.10 0.12 0.14
MATERIAL PRICES AND LABOR UNITS FOR RE-BAR AND CHASING CONCRETE ARE PER FOOT
MATERIAL PRICES AND LABOR UNITS FOR HOLE DIGGING AND MISCELLANEOUS ARE PER EACH
NPG AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
8-2 COPYRIGHT © 1996-2018 by ELECTRICAL RESOURCES, INC.